$40,000 pre-application assessment; $250,000 per cluster study; customers pay 100% of required transmission and substation costs, with 60% of shared cluster-study costs and infrastructure costs identified
From agendapacket
Document date
Nov 4, 2026

The 30-second brief

What it covers

The committee discussed Salt River Project’s electric-service requirements for potential data centers in Florence Tech Park. SRP’s process includes a 15-year service agreement, customer-funded infrastructure, study charges, minimum demand commitments, and collateral requirements.

Who holds it

Salt River Project (Srp) holds this utilities contract with Town of Florence. Its other public contracts on record include work for City of Chandler.

What happens next

Term as filed: 15-year Agreement for Electric Service; collateral held during construction and for five years after energization.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Utilities
Amount
$40,000 pre-application assessment; $250,000 per cluster study; customers pay 100% of required transmission and substation costs, with 60% of shared cluster-study costs and infrastructure costs identified
Document date
November 4, 2026
Term
15-year Agreement for Electric Service; collateral held during construction and for five years after energization
Source document
Town of Florence AgendaPacket Data Center Facility Ad Hoc Advisory Committee Meeting 2026-11-04 (AgendaPacket)

Salt River Project (Srp)'s other public contracts

More Town of Florence contracts

Questions about this contract

Who was awarded the utilities contract by Town of Florence?

Salt River Project (Srp) was awarded this utilities contract by Town of Florence, as recorded on November 4, 2026. The contract value is $40,000 pre-application assessment; $250,000 per cluster study; customers pay 100% of required transmission and substation costs, with 60% of shared cluster-study costs and infrastructure costs identified.

How much is the Salt River Project (Srp) contract with Town of Florence worth?

The Salt River Project (Srp) contract with Town of Florence is valued at $40,000 pre-application assessment; $250,000 per cluster study; customers pay 100% of required transmission and substation costs, with 60% of shared cluster-study costs and infrastructure costs identified, covering utilities work.

What type of contract is this?

This is a Utilities contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Town of Florence AgendaPacket Data Center Facility Ad Hoc Advisory Committee Meeting 2026-11-04 (AgendaPacket), dated November 4, 2026 from Town of Florence. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Salt River Project (Srp) hold?

Salt River Project (Srp) may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Town of Florence currently buying?

Explore Town of Florence's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →