CONTRACTAMENDED

Soderberg Water Main Contract Finalized Below Original Amount

Caribou Utilities District logoCaribou Utilities District
Disclosed value
$1,462,617.50 final construction cost; original contract amount $1,472,750
From agendapacket
Document date
Nov 10, 2026

The 30-second brief

What it covers

Caribou Utilities District approved the final balancing change order for Soderberg Construction’s Water Main River Crossing Project. The project’s final construction cost is $1,462,617.50, $10,132.50 below the original contract amount, with minor restoration work remaining for spring 2027.

Who holds it

Soderberg Construction holds this construction contract with Caribou Utilities District. Its other public contracts on record include work for City of Caribou.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$1,462,617.50 final construction cost; original contract amount $1,472,750
Document date
November 10, 2026
Source document
Caribou Utilities District AgendaPacket Board of Trustees Meeting 2026-11-10 (AgendaPacket)

Soderberg Construction's other public contracts

More Caribou Utilities District contracts

Questions about this contract

Who was awarded the construction contract by Caribou Utilities District?

Soderberg Construction was awarded this construction contract by Caribou Utilities District, as recorded on November 10, 2026. The contract value is $1,462,617.50 final construction cost; original contract amount $1,472,750.

How much is the Soderberg Construction contract with Caribou Utilities District worth?

The Soderberg Construction contract with Caribou Utilities District is valued at $1,462,617.50 final construction cost; original contract amount $1,472,750, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Caribou Utilities District AgendaPacket Board of Trustees Meeting 2026-11-10 (AgendaPacket), dated November 10, 2026 from Caribou Utilities District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Soderberg Construction hold?

Soderberg Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Caribou Utilities District currently buying?

Explore Caribou Utilities District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →

The coverage behind every signal

agencies covered
100,000+agencies covered
buying signals a week
400,000+buying signals a week
decision makers
2.6M+decision makers
in government spend tracked
$14T+in government spend tracked

Trusted by 200+ enterprise teams

Motive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logo