Batavia School District Approves Earthtech Site Work Change Order
- Disclosed value
- Increase of $7,386.00; new Contract Sum $6,121,573.00
- From report
- Document date
- Sep 23, 2026
The 30-second brief
Batavia City School District amended Earthtech Developers’ Phase 3 site-work contract by approximately $7,386 to remove concrete louver pads and extend the asphalt walkway at Batavia Senior High School. The change leaves the contract schedule unchanged and raises the total contract value to $6,121,573.
Earthtech Developers LLC holds this construction contract with Batavia City School District. Its other public contracts on record include work for Oakfield-Alabama Central School District and Town of Ontario.
Term as filed: Contract time unchanged; zero (0) days added.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Increase of $7,386.00; new Contract Sum $6,121,573.00
- Document date
- September 23, 2026
- Term
- Contract time unchanged; zero (0) days added
- Vendor
- Earthtech Developers LLC
- Source document
- Batavia City School District Report Change Order Package for Phase 3 2026-09-23 (Report)
Earthtech Developers LLC's other public contracts
More Batavia City School District contracts
Questions about this contract
Who was awarded the construction contract by Batavia City School District?
Earthtech Developers LLC was awarded this construction contract by Batavia City School District, as recorded on September 23, 2026. The contract value is Increase of $7,386.00; new Contract Sum $6,121,573.00.
How much is the Earthtech Developers LLC contract with Batavia City School District worth?
The Earthtech Developers LLC contract with Batavia City School District is valued at Increase of $7,386.00; new Contract Sum $6,121,573.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Batavia City School District Report Change Order Package for Phase 3 2026-09-23 (Report), dated September 23, 2026 from Batavia City School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Earthtech Developers LLC hold?
Earthtech Developers LLC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Batavia City School District currently buying?
Explore Batavia City School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.