Mukwonago Recommends Musson Brothers Roadwork Change Order
Mukwonago villageCity · WI- Disclosed value
- Approximately $35,000 funding shortfall after project changes; approximately $50,000 reallocated to address gap
- From agendapacket
- Document date
- Nov 4, 2026
The 30-second brief
Mukwonago officials recommended a change order with Musson Brothers for additional Field Park entrances, roads, and parking improvements. The changes add 25 parking stalls and create an anticipated funding shortfall of about $35,000.
Musson Brothers Inc holds this construction contract with Mukwonago village. Its other public contracts on record include work for Menomonee Falls village and City of Beresford.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Approximately $35,000 funding shortfall after project changes; approximately $50,000 reallocated to address gap
- Document date
- November 4, 2026
- Vendor
- Musson Brothers Inc
- Agency
- Mukwonago village
- Source document
- Village of Mukwonago AgendaPacket Committee of the Whole Meeting 2026-11-04 (AgendaPacket)
Musson Brothers Inc's other public contracts
More Mukwonago village contracts
Questions about this contract
Who was awarded the construction contract by Mukwonago village?
Musson Brothers Inc was awarded this construction contract by Mukwonago village, as recorded on November 4, 2026. The contract value is Approximately $35,000 funding shortfall after project changes; approximately $50,000 reallocated to address gap.
How much is the Musson Brothers Inc contract with Mukwonago village worth?
The Musson Brothers Inc contract with Mukwonago village is valued at Approximately $35,000 funding shortfall after project changes; approximately $50,000 reallocated to address gap, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Village of Mukwonago AgendaPacket Committee of the Whole Meeting 2026-11-04 (AgendaPacket), dated November 4, 2026 from Mukwonago village. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Musson Brothers Inc hold?
Musson Brothers Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Mukwonago village currently buying?