CONSTRUCTIONPENDING

Stadium Drainage Change Order Drafted for Tedesco Excavating

Moon Area School District drafted Change Order SC-CO-06 with Tedesco Excavating & Paving, Inc. for revised drainage and aggregate sitework at the Stadium Facilities project. The change order would increase the contract by $26,302.97, bringing the total to $5,814,745.92, with no change to the contract time.

Document date · September 24, 2026

Track Moon Area SD contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Moon Area SD.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$26,302.97 increase; new contract sum $5,814,745.92
Contract type
CONSTRUCTION
Contract term
Contract time unchanged; substantial completion dates remain as per the original contract
Renewal
Change Order SC-CO-06; contract time remains unchanged and the change order requires signatures from all designated parties to become valid.
Document type
Contract
Source document
Moon Area School District Contract Change Order SC-CO-06 Stadium Facilities Sitework Construction 2026-09-24

Related contracts

Other contracts from Tedesco Excavating & Paving Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Moon Area SD?

Tedesco Excavating & Paving Inc was awarded this construction contract by Moon Area SD, as recorded on September 24, 2026. The contract value is $26,302.97 increase; new contract sum $5,814,745.92.

How much is the Tedesco Excavating & Paving Inc contract with Moon Area SD worth?

The Tedesco Excavating & Paving Inc contract with Moon Area SD is valued at $26,302.97 increase; new contract sum $5,814,745.92, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Moon Area School District Contract Change Order SC-CO-06 Stadium Facilities Sitework Construction 2026-09-24 (Contract), dated September 24, 2026 from Moon Area SD. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Tedesco Excavating & Paving Inc hold?

Tedesco Excavating & Paving Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Tedesco Excavating & Paving Inc's profile

What is Moon Area SD currently buying?

Explore Moon Area SD's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Moon Area SD's profile