University of Florida - Replacement of the Rabon Plant Cooling Towers 4 and 5 - FY27-ITN-001 (2026)
- Due
- Aug 20, 2026
- Deadline passed
- Posted
- Jul 9, 2026
- Primary contact
- Mike Loudis
- (352) 294-1154
The 30-second brief
University of Florida seeks competitive proposals for the disposal and replacement of two cell Marley cooling towers 4 and 5 at the Lacy C. Rabon Chilled Water Plant, located at 1858 Mowry Road, Building 0473, Gainesville, FL 32608. The scope includes replacing the structure utilizing an existing ~40ft x 50ft basin footprint, furnishing and installing 480V 60HP fan motors, vibration switches, motor space heaters, pole lights, oil level switches, mechanical piping, metal fan blades, gearboxes, fill, and drift eliminators. Project budget is $950,000.00 with a mandatory pre-bid site visit on 07/17/2026 and submission deadline of 08/20/2026 at 3:00 PM EDT. Work is scheduled to commence on November 1, 2026, and must be fully operational no later than April 1, 2027.
2 Cell Marley Cooling Towers 4 and 5, 2 - 480V 60HP fan motors and associated fans, 2 - 120V vibration switches, 2 - 120V motor space heaters, 4 - pole lights on top of tower, Vibration switches, Oil level switch, Safety switches, Mechanical piping and connections, Cooling tower fans and gearboxes, Cooling tower fill, Drift eliminators, Fan/gearbox lube oil system, Staircase and access, Temporary cooling tower
Technical proposal including ability to complete work no later than April 1, 2027, Pricing Proposal, Evidence of satisfactory performance on five similar projects within the past five years, References (Trade, Bank, Surety), Professional services offered and support options, Agreement with UF standard Terms & Conditions and technical specifications, Material and workmanship warranty
Get notified when University Of Florida posts the next one.
Get alerts freeFree account · 30-second setup · No credit card
Summary
University of Florida seeks competitive proposals for the disposal and replacement of two cell Marley cooling towers 4 and 5 at the Lacy C. Rabon Chilled Water Plant, located at 1858 Mowry Road, Building 0473, Gainesville, FL 32608.
The scope includes replacing the structure utilizing an existing ~40ft x 50ft basin footprint, furnishing and installing 480V 60HP fan motors, vibration switches, motor space heaters, pole lights, oil level switches, mechanical piping, metal fan blades, gearboxes, fill, and drift eliminators. Project budget is $950,000.00 with a mandatory pre-bid site visit on 07/17/2026 and submission deadline of 08/20/2026 at 3:00 PM EDT. Work is scheduled to commence on November 1, 2026, and must be fully operational no later than April 1, 2027.
EVALUATION CRITERIA
Technical proposal including ability to complete work no later than April 1, 2027, Pricing Proposal, Evidence of satisfactory performance on five similar projects within the past five years, References (Trade, Bank, Surety), Professional services offered and support options, Agreement with UF standard Terms & Conditions and technical specifications, Material and workmanship warranty
REQUIRED DELIVERABLES
15- 2 Cell Marley Cooling Towers 4 and 5
- 2 - 480V 60HP fan motors and associated fans
- 2 - 120V vibration switches
- 2 - 120V motor space heaters
- 4 - pole lights on top of tower
- Vibration switches
- Oil level switch
- Safety switches
- Mechanical piping and connections
- Cooling tower fans and gearboxes
- Cooling tower fill
- Drift eliminators
- Fan/gearbox lube oil system
- Staircase and access
- Temporary cooling tower
REQUIRED ATTACHMENTS
Certification of Proposal, evidence of satisfactory performance on five similar projects, trade references, bank references, surety references, list of all subcontractors for work valued at more than $10,000, proof of corporation, proof of liability insurance coverage, EMR for the past three years, minimum material and workmanship warranty, list of spare parts and additional charges
- Submit to
- https://app01.jaggaer.com/apps/Router/ViewSourcingEvent?AuthToken=1%3AAES2%23CEArKgTyskAI9SN3tEEwyRUJVsXbDQe7fr1kSFDc%2F
- Scope location
- Gainesville, FL
- Reported agency
- University of Florida
Questions about this RFP
How do I respond to this RFP from University Of Florida?
Review the full solicitation document for submission requirements, evaluation criteria, and deadlines. The submission deadline is August 20, 2026. The solicitation specifies required deliverables that must be addressed in your response. Be sure to include all required attachments as outlined in the solicitation. Submissions should be delivered to: https://app01.jaggaer.com/apps/Router/ViewSourcingEvent?AuthToken=1%3AAES2%23CEArKgTyskAI9SN3tEEwyRUJVsXbDQe7fr1kSFDc%2F. For questions, contact Mike Loudis.
Can small businesses or minority-owned firms bid on this RFP?
Most government agencies, including University Of Florida in FL, encourage participation from small businesses, minority-owned, women-owned, and disadvantaged business enterprises (MBE/WBE/DBE). Check the full solicitation for any small business participation goals.
What happens after the RFP submission deadline?
After the deadline, the issuing agency reviews all submissions against the stated evaluation criteria. This typically includes a compliance check, technical evaluation, cost analysis, and may involve oral presentations with shortlisted vendors.
Can I ask questions about this solicitation before submitting?
Yes, most solicitations allow vendors to submit questions during a designated period. The primary contact is Mike Loudis at (352) 294-1154. Questions and answers are typically shared with all prospective bidders.
What are the key deliverables?
The solicitation specifies the following deliverables: 2 Cell Marley Cooling Towers 4 and 5, 2 - 480V 60HP fan motors and associated fans, 2 - 120V vibration switches, 2 - 120V motor space heaters, 4 - pole lights on top of tower, Vibration switches, Oil level switch, Safety switches, Mechanical piping and connections, Cooling tower fans and gearboxes,. Proposals should clearly address how each deliverable will be met.
Show 4 more questions
What are the evaluation criteria for this solicitation?
This solicitation includes specific evaluation criteria that will be used to score proposals. The criteria include: "Technical proposal including ability to complete work no later than April 1, 2027, Pricing Proposal, Evidence of satisfactory performance on five similar projects within the past five years, Reference..." Vendors should carefully align their proposals with each criterion to maximize their score.
Where can I find more RFPs from University Of Florida?
All active and historical solicitations from University Of Florida are tracked and searchable. As a higher ed agency, University Of Florida regularly publishes solicitations. Visit the agency profile to see current open bids, past contracts, vendor relationships, and decision-maker contacts.
What documents are required to bid on this RFP?
Requirements vary by solicitation, but common documents include a technical proposal, cost/price proposal, proof of insurance, relevant certifications, past performance references, and any forms specified in the solicitation. This solicitation specifically requires the following attachments: Certification of Proposal, evidence of satisfactory performance on five similar projects, trade references, bank references, surety references, list of all subcontractors for work valued at more than. Review the full document from University Of Florida for the complete list.
What is the scope of this project?
This solicitation defines a specific project scope. The scope covers the following locations: Gainesville, FL. Review the full solicitation for detailed scope requirements.