Hangar Construction Schedule Extended by Change Order
- Document date
- Nov 7, 2026
The 30-second brief
The Federal Aviation Administration reported ongoing construction work by Approach B-D Construction, Inc. for a 2-bay box hangar and approach at Crete Municipal Airport. The project schedule includes a 170-calendar-day change order for Phase 1 and a 15-working-day Phase 2; no work occurred during the week ending November 7, 2026 because the site was too wet.
Approach B-d Construction Inc holds this construction contract with City of Crete.
Term as filed: Phase 1: 170 calendar days including change order; Phase 2: 15 working days.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- November 7, 2026
- Term
- Phase 1: 170 calendar days including change order; Phase 2: 15 working days
- Vendor
- Approach B-d Construction Inc
- Agency
- City of Crete
- Source document
- Federal Aviation Administration Report Construction Progress and Inspection Report - Week 12 2026-11-07 (Report)
More City of Crete contracts
Questions about this contract
Who was awarded the construction contract by City of Crete?
Approach B-d Construction Inc was awarded this construction contract by City of Crete, as recorded on November 7, 2026.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Federal Aviation Administration Report Construction Progress and Inspection Report - Week 12 2026-11-07 (Report), dated November 7, 2026 from City of Crete. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What is City of Crete currently buying?
Explore City of Crete's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.