Belton Approves $370,806 Water Meter Change Order
- Disclosed value
- Increase of $370,806.24; new contract price $8,621,478.64
- From resolution
- Document date
- Aug 25, 2026
The 30-second brief
The City of Belton approved a $370,806.24 change order for Utility Service Company, Inc.'s advanced metering infrastructure replacement project. The adjustment corrects meter quantities and sizes, increasing the contract total from $8,250,672.40 to $8,621,478.64 with no change to the completion time.
Utility Service Company Inc holds this construction contract with City of Belton. Its other public contracts on record include work for Town of Greentown and Palatine village.
Term as filed: Effective July 16, 2026; contract time increased by 0 days.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Increase of $370,806.24; new contract price $8,621,478.64
- Document date
- August 25, 2026
- Term
- Effective July 16, 2026; contract time increased by 0 days
- Agency
- City of Belton
- Source document
- City of Belton Resolution R2026-084 Approving Change Order No. 1 for Water Meter Infrastructure Replacement Implementation Project 2026-08-25 (Resolution)
Utility Service Company Inc's other public contracts
More City of Belton contracts
Questions about this contract
Who was awarded the construction contract by City of Belton?
Utility Service Company Inc was awarded this construction contract by City of Belton, as recorded on August 25, 2026. The contract value is Increase of $370,806.24; new contract price $8,621,478.64.
How much is the Utility Service Company Inc contract with City of Belton worth?
The Utility Service Company Inc contract with City of Belton is valued at Increase of $370,806.24; new contract price $8,621,478.64, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a resolution record.
Where was this contract approved?
This contract appears in City of Belton Resolution R2026-084 Approving Change Order No. 1 for Water Meter Infrastructure Replacement Implementation Project 2026-08-25 (Resolution), dated August 25, 2026 from City of Belton. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Utility Service Company Inc hold?
Utility Service Company Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Belton currently buying?
Explore City of Belton's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.