City of Augusta Awards Construction Contract to Pratt & Sons Inc (September 2026)
City of AugustaCity · Augusta, ME- Awarded
- Sep 17, 2026
The 30-second brief
The City of Augusta awarded the Ward Road Full Depth Reclamation project to Pratt & Sons, Inc. Construction is scheduled to begin the week of September 21, 2026, and is expected to take three to four weeks, depending on weather.
Pratt & Sons Inc holds this construction contract with City of Augusta. Its other public contracts on record include work for State of Maine and City of Lewiston.
Term as filed: Scheduled to start the week of September 21, 2026; expected to take three to four weeks, depending on weather.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- September 17, 2026
- Term
- Scheduled to start the week of September 21, 2026; expected to take three to four weeks, depending on weather
- Vendor
- Pratt & Sons Inc
- Agency
- City of Augusta
- Source document
- City of Augusta AgendaPacket Business Meeting 2026-09-17 (AgendaPacket)
Pratt & Sons Inc's other public contracts
More City of Augusta contracts
Questions about this contract
Who was awarded the construction contract by City of Augusta?
Pratt & Sons Inc was awarded this construction contract by City of Augusta, as recorded on September 17, 2026.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in City of Augusta AgendaPacket Business Meeting 2026-09-17 (AgendaPacket), dated September 17, 2026 from City of Augusta. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What is City of Augusta currently buying?
Explore City of Augusta's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.