Ute Water Conservancy District - Process Water Lagoon Improvements - 2026
Ute Water Conservancy DistrictSpecial District · Grand Junction, CO- Due
- Mar 20, 2026
- Deadline passed
- Primary contact
- Dave Payne
- (970) 256-2855
The 30-second brief
Ute Water Conservancy District invites sealed bids for the Process Water Lagoon Improvements project in Grand Junction, Colorado. The scope of work includes the construction of two concrete lagoon structures with underdrain systems, a pump station, approximately 930 linear feet of 12-inch C900 PVC force main, approximately 1,760 linear feet of 24-inch PS46 PVC pipe, site grading, and related miscellaneous work. Sealed bids are due by 2:00 P.M. on Friday, March 20, 2026, at the Administration Office located at 2190 H 1/4 Rd, Grand Junction, Colorado 81505. A mandatory pre-bid meeting is scheduled for Wednesday, March 4, 2026, at 1:00 P.M. at the Water Treatment Plant located at 3975 Rapid Creek Road, Palisade, Colorado. Bidders are required to provide a five percent (5%) Bid Bond and one hundred percent (100%) Performance and Payment Bonds.
Two concrete lagoon structures with underdrain systems, Pump station, Approximately 930 linear feet (LF) of 12-inch C900 PVC force main, Approximately 1, 760 LF of 24” PS46 PVC pipe, Site grading
Hear what Ute Water Conservancy District plans next before it's posted.
Get alerts freeFree account · 30-second setup · No credit card
Summary
Ute Water Conservancy District invites sealed bids for the Process Water Lagoon Improvements project in Grand Junction, Colorado.
The scope of work includes the construction of two concrete lagoon structures with underdrain systems, a pump station, approximately 930 linear feet of 12-inch C900 PVC force main, approximately 1,760 linear feet of 24-inch PS46 PVC pipe, site grading, and related miscellaneous work. Sealed bids are due by 2:00 P.M. on Friday, March 20, 2026, at the Administration Office located at 2190 H 1/4 Rd, Grand Junction, Colorado 81505. A mandatory pre-bid meeting is scheduled for Wednesday, March 4, 2026, at 1:00 P.M. at the Water Treatment Plant located at 3975 Rapid Creek Road, Palisade, Colorado. Bidders are required to provide a five percent (5%) Bid Bond and one hundred percent (100%) Performance and Payment Bonds.
REQUIRED DELIVERABLES
Two concrete lagoon structures with underdrain systems, Pump station, Approximately 930 linear feet (LF) of 12-inch C900 PVC force main, Approximately 1, 760 LF of 24” PS46 PVC pipe, Site grading
REQUIRED ATTACHMENTS
5% Bid Bond, 100% Performance and Payment Bonds
- Submit to
- Administration Office, 2190 H 1/4 Rd, Grand Junction, Colorado 81505
- Scope location
- Grand Junction, Colorado
Questions about this BID
How do I respond to this Bid from Ute Water Conservancy District?
Review the full solicitation document for submission requirements, evaluation criteria, and deadlines. The submission deadline is March 20, 2026. The solicitation specifies required deliverables that must be addressed in your response. Be sure to include all required attachments as outlined in the solicitation. Submissions should be delivered to: Administration Office, 2190 H 1/4 Rd, Grand Junction, Colorado 81505. For questions, contact Dave Payne.
Can small businesses or minority-owned firms bid on this Bid?
Most government agencies, including Ute Water Conservancy District in CO, encourage participation from small businesses, minority-owned, women-owned, and disadvantaged business enterprises (MBE/WBE/DBE). Check the full solicitation for any small business participation goals.
What happens after the Bid submission deadline?
After the deadline, the issuing agency reviews all submissions against the stated evaluation criteria. This typically includes a compliance check, technical evaluation, cost analysis, and may involve oral presentations with shortlisted vendors.
Can I ask questions about this solicitation before submitting?
Yes, most solicitations allow vendors to submit questions during a designated period. The primary contact is Dave Payne at (970) 256-2855. Questions and answers are typically shared with all prospective bidders.
What are the key deliverables?
The solicitation specifies the following deliverables: Two concrete lagoon structures with underdrain systems, Pump station, Approximately 930 linear feet (LF) of 12-inch C900 PVC force main, Approximately 1, 760 LF of 24” PS46 PVC pipe, Site grading. Proposals should clearly address how each deliverable will be met.
Show 3 more questions
Where can I find more RFPs from Ute Water Conservancy District?
All active and historical solicitations from Ute Water Conservancy District are tracked and searchable. As a special district agency, Ute Water Conservancy District regularly publishes solicitations. Visit the agency profile to see current open bids, past contracts, vendor relationships, and decision-maker contacts.
What documents are required to bid on this Bid?
Requirements vary by solicitation, but common documents include a technical proposal, cost/price proposal, proof of insurance, relevant certifications, past performance references, and any forms specified in the solicitation. This solicitation specifically requires the following attachments: 5% Bid Bond, 100% Performance and Payment Bonds. Review the full document from Ute Water Conservancy District for the complete list.
What is the scope of this project?
This solicitation defines a specific project scope. The scope covers the following locations: Grand Junction, Colorado. Review the full solicitation for detailed scope requirements.