RFPCLOSED
Save

Santa Clara Valley Transportation Authority CMGC Chaboya Yard ZEB Infrastructure RFP

Santa Clara Valley Transportation Authority logoSanta Clara Valley Transportation Authority
Due
Sep 25, 2026
Deadline passed
Posted
Jul 14, 2026
Primary contact
Karmjot Singh
(408) 888-9967

The 30-second brief

What they're buying

The Santa Clara Valley Transportation Authority (VTA) is soliciting proposals for a Construction Manager/General Contractor (CMGC) for the Chaboya Yard Zero-Emission Bus (ZEB) Charging Infrastructure Project. The scope includes preconstruction services such as design collaboration, constructability reviews, value engineering, and scheduling, with the potential for construction services via a Guaranteed Maximum Price (GMP) amendment. Key assets involve medium-voltage switchgear, transformers, charging cabinets, and overhead pantograph dispensers. The project budget is estimated between $15M and $20M, with a targeted construction completion of Summer 2029. Preconstruction services are expected within 240 days of a notice to proceed. Proposals are due September 25, 2026, to the VTA office in San Jose, CA.

What you must deliver

Preconstruction Services, Plans, Specifications, And Estimate (PS&E) support, GMP proposal

How it's scored

Qualifications, competence, capacity, specific approach

Hear what Santa Clara Valley Transportation Authority plans next before it's posted.

Get alerts free

Free account · 30-second setup · No credit card

Summary

The Santa Clara Valley Transportation Authority (VTA) is soliciting proposals for a Construction Manager/General Contractor (CMGC) for the Chaboya Yard Zero-Emission Bus (ZEB) Charging Infrastructure Project.

The scope includes preconstruction services such as design collaboration, constructability reviews, value engineering, and scheduling, with the potential for construction services via a Guaranteed Maximum Price (GMP) amendment. Key assets involve medium-voltage switchgear, transformers, charging cabinets, and overhead pantograph dispensers. The project budget is estimated between $15M and $20M, with a targeted construction completion of Summer 2029. Preconstruction services are expected within 240 days of a notice to proceed. Proposals are due September 25, 2026, to the VTA office in San Jose, CA.

EVALUATION CRITERIA

4
  • Qualifications
  • Competence
  • Capacity
  • Specific approach

REQUIRED DELIVERABLES

5
  • Preconstruction Services
  • Plans
  • Specifications
  • Estimate (PS&E) support
  • GMP proposal
Submit to
3331 N 1st Street, Building B1, San Jose, CA, 95134

Questions about this RFP

How do I respond to this RFP from Santa Clara Valley Transportation Authority?

Review the full solicitation document for submission requirements, evaluation criteria, and deadlines. The submission deadline is September 25, 2026. The solicitation specifies required deliverables that must be addressed in your response. Submissions should be delivered to: 3331 N 1st Street, Building B1, San Jose, CA, 95134. For questions, contact Karmjot Singh.

Can small businesses or minority-owned firms bid on this RFP?

Most government agencies, including Santa Clara Valley Transportation Authority in CA, encourage participation from small businesses, minority-owned, women-owned, and disadvantaged business enterprises (MBE/WBE/DBE). Check the full solicitation for any small business participation goals.

What happens after the RFP submission deadline?

After the deadline, the issuing agency reviews all submissions against the stated evaluation criteria. This typically includes a compliance check, technical evaluation, cost analysis, and may involve oral presentations with shortlisted vendors.

Can I ask questions about this solicitation before submitting?

Yes, most solicitations allow vendors to submit questions during a designated period. The primary contact is Karmjot Singh at (408) 888-9967. Questions and answers are typically shared with all prospective bidders.

What are the key deliverables?

The solicitation specifies the following deliverables: Preconstruction Services, Plans, Specifications, And Estimate (PS&E) support, GMP proposal. Proposals should clearly address how each deliverable will be met.

Show 3 more questions

What are the evaluation criteria for this solicitation?

This solicitation includes specific evaluation criteria that will be used to score proposals. The criteria include: "Qualifications, competence, capacity, specific approach" Vendors should carefully align their proposals with each criterion to maximize their score.

Where can I find more RFPs from Santa Clara Valley Transportation Authority?

All active and historical solicitations from Santa Clara Valley Transportation Authority are tracked and searchable. As a public authority agency, Santa Clara Valley Transportation Authority regularly publishes solicitations. Visit the agency profile to see current open bids, past contracts, vendor relationships, and decision-maker contacts.

What documents are required to bid on this RFP?

Requirements vary by solicitation, but common documents include a technical proposal, cost/price proposal, proof of insurance, relevant certifications, past performance references, and any forms specified in the solicitation. Review the full document from Santa Clara Valley Transportation Authority for the complete list.

Work in government? Get Civic IQ free →

Start finding government buyers today.
It's free.

B2G and SLED sales intelligence. Surface government procurement signals from 100,000+ state, local, and education agencies months before the RFP.

Get started free

No credit card required