Airport Plans $2 Million McCarthy Contract Increase
- Disclosed value
- $2,000,000 increase; Final Guaranteed Maximum Price of $228,751,325
- From agenda
- Document date
- Nov 13, 2026
The 30-second brief
The Airport Commission is scheduled to approve a $2 million Phase D6 increase for McCarthy Building Companies, Inc.'s International Terminal Building Phase 2 design-build contract. The amendment would raise the final guaranteed maximum price to $228.751 million and extend the contract to 2,507 calendar days.
Mccarthy Building Companies Inc holds this construction contract with San Francisco International Airport. Its other public contracts on record include work for Successor Agency To The Redevelopment Agency For The County Of Riverside, California and Reno-Tahoe Airport Authority.
Term as filed: Extended to 2,507 consecutive calendar days.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $2,000,000 increase; Final Guaranteed Maximum Price of $228,751,325
- Document date
- November 13, 2026
- Term
- Extended to 2,507 consecutive calendar days
- Source document
- San Francisco Airport Commission Agenda November 17, 2026 (Agenda)
Mccarthy Building Companies Inc's other public contracts
More San Francisco International Airport contracts
Questions about this contract
Who was awarded the construction contract by San Francisco International Airport?
Mccarthy Building Companies Inc was awarded this construction contract by San Francisco International Airport, as recorded on November 13, 2026. The contract value is $2,000,000 increase; Final Guaranteed Maximum Price of $228,751,325.
How much is the Mccarthy Building Companies Inc contract with San Francisco International Airport worth?
The Mccarthy Building Companies Inc contract with San Francisco International Airport is valued at $2,000,000 increase; Final Guaranteed Maximum Price of $228,751,325, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record, structured as a not-to-exceed (ceiling) agreement.
Where was this contract approved?
This contract appears in San Francisco Airport Commission Agenda November 17, 2026 (Agenda), dated November 13, 2026 from San Francisco International Airport. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Mccarthy Building Companies Inc hold?
Mccarthy Building Companies Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is San Francisco International Airport currently buying?
Explore San Francisco International Airport's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.