- Disclosed value
- $29,785,236.00 contract award; $80,000.00 pre-construction fee; Coble GMP #2 $16,380,462.00; Howard GMP #2 $12,432,560.00; Early Flooring Coble $967,084.00
- From report
- Document date
- Nov 9, 2026
- Renews
- Free account
The 30-second brief
Mansfield Independent School District continues Lee Lewis’s $29,785,236 Package 2 contract for fine arts additions and life-cycle replacements at Howard and Coble middle schools. The work is scheduled for completion by June 2027.
Lee Lewis holds this construction contract with Mansfield Independent School District. Its other public contracts on record include work for Garland Independent School District.
The renewal date is on record. Get free alerts for pre-RFPs like this one, matched to what you sell.
Get pre-RFPs for work like this before the bid is out.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $29,785,236.00 contract award; $80,000.00 pre-construction fee; Coble GMP #2 $16,380,462.00; Howard GMP #2 $12,432,560.00; Early Flooring Coble $967,084.00
- Document date
- November 9, 2026
- Term
- Ongoing; completion scheduled by June 2027
- Renews
- On record
- Vendor
- Lee Lewis
- Source document
- Mansfield Independent School District Report 2024 Bond Program Executive Program Summary November 2026 2026-11-09 (Report)
Lee Lewis's other public contracts
More Mansfield Independent School District contracts
Questions about this contract
Who was awarded the construction contract by Mansfield Independent School District?
Lee Lewis was awarded this construction contract by Mansfield Independent School District, as recorded on November 9, 2026. The contract value is $29,785,236.00 contract award; $80,000.00 pre-construction fee; Coble GMP #2 $16,380,462.00; Howard GMP #2 $12,432,560.00; Early Flooring Coble $967,084.00.
How much is the Lee Lewis contract with Mansfield Independent School District worth?
The Lee Lewis contract with Mansfield Independent School District is valued at $29,785,236.00 contract award; $80,000.00 pre-construction fee; Coble GMP #2 $16,380,462.00; Howard GMP #2 $12,432,560.00; Early Flooring Coble $967,084.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Mansfield Independent School District Report 2024 Bond Program Executive Program Summary November 2026 2026-11-09 (Report), dated November 9, 2026 from Mansfield Independent School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Lee Lewis hold?
Lee Lewis may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Mansfield Independent School District currently buying?