Heath De Leon Pump Station Change Order Proposed
- Disclosed value
- $2,194,212.11 (change order increase); original contract $20,316,180; Change Order 1 -$23,771.19
- From agenda
- Document date
- Aug 12, 2026
The 30-second brief
The El Paso Water Public Service Board is asked to approve Change Order No. 2 with Smithco Construction Inc. for the Heath De Leon Pump Station Replacement project, adding $2,194,212.11 to the original $20,316,180 construction contract. The change order extends the schedule by 240 days to complete additional pipeline, access, street, and retaining wall work coordinated with an adjacent housing project.
Smithco Construction Inc holds this construction contract with El Paso Water. Its other public contracts on record include work for City of Carlsbad.
Term as filed: Original term plus 324 days (Change Order 1) plus 240 days (Change Order 2).
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $2,194,212.11 (change order increase); original contract $20,316,180; Change Order 1 -$23,771.19
- Document date
- August 12, 2026
- Term
- Original term plus 324 days (Change Order 1) plus 240 days (Change Order 2)
- Vendor
- Smithco Construction Inc
- Agency
- El Paso Water
- Source document
- El Paso Water Agenda Item Change Order 2 Heath De Leon Pump Station Replacement 2026-08-12 (Agenda)
Smithco Construction Inc's other public contracts
More El Paso Water contracts
Questions about this contract
Who was awarded the construction contract by El Paso Water?
Smithco Construction Inc was awarded this construction contract by El Paso Water, as recorded on August 12, 2026. The contract value is $2,194,212.11 (change order increase); original contract $20,316,180; Change Order 1 -$23,771.19.
How much is the Smithco Construction Inc contract with El Paso Water worth?
The Smithco Construction Inc contract with El Paso Water is valued at $2,194,212.11 (change order increase); original contract $20,316,180; Change Order 1 -$23,771.19, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in El Paso Water Agenda Item Change Order 2 Heath De Leon Pump Station Replacement 2026-08-12 (Agenda), dated August 12, 2026 from El Paso Water. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Smithco Construction Inc hold?
Smithco Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is El Paso Water currently buying?
Explore El Paso Water's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.