Wastewater project transformer need
Lamar Light And PowerColorado- Detected
- Oct 13, 2026
- 22 days ago
- Sector
- Utilities
- Est. value
- Free account
Get pre-RFPs like this one before they're bid.
Get briefs like this freeFree account · 30-second setup · No credit card
From the meeting
At the October 13, 2026 meeting, Superintendent Houssin A. Hourieh reported that an electrical engineer designing the Lamar Waste Water Project south of the river between Cty. Rd.
8 and 10 said the project needs a 1,000 KVA padmount transformer. The transformer was estimated to cost about $60,000. The design was about 60% complete and was expected to go out for bid in January or February 2027, with construction beginning in April 2027.
Decision state: planning and pre-bid.
- Meeting date
- October 13, 2026
- Agency
- Lamar Light And Power
Questions about this project
What is a pre-RFP?
A pre-RFP is an early indicator that a government agency is planning a purchase — a project discussed in a board meeting, a budget line item, a new hire, or a grant award — captured before a formal RFP or bid is published. Acting on pre-RFPs gives SLED and B2G vendors months of lead time to build relationships and shape requirements.
When will Lamar Light And Power issue an RFP for this project?
Pre-RFPs typically surface 6–18 months before a formal solicitation is published. Civic IQ tracks Lamar Light And Power's meeting records, agendas, and budgets continuously and updates this pre-RFP as the project moves through the buying cycle toward an RFP.
How can vendors engage with Lamar Light And Power before the RFP is published?
Vendors who reach out during the planning window can help shape requirements and build relationships with the decision-makers running the project. A free Civic IQ account sends you the pre-RFPs that fit what you sell, with the AI brief and the decision makers for the top matches in each digest.
Where can I find more utilities government opportunities in Colorado?
Civic IQ monitors board meetings, agendas, budgets, and capital plans from 100,000+ state and local agencies and surfaces utilities pre-RFPs in Colorado as soon as they appear — months before they reach bid portals.