Windler Ratifies 89-Day Dynalectric Project Extension

Windler Public Improvement Authority
Document date
Mar 30, 2026
Term
Time extension of 89 calendar days

The 30-second brief

What it covers

The Windler Public Improvement Authority ratified Change Order No. 4 with Dynalectric Company. The change order extends the Windler Connector Roads #1 streetlights project by 89 calendar days.

Who holds it

Dynalectric Company holds this construction contract with Windler Public Improvement Authority. Its other public contracts on record include work for HM Metropolitan District Nos. 1-9.

What happens next

Term as filed: Time extension of 89 calendar days.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Document date
March 30, 2026
Term
Time extension of 89 calendar days
Source document
Windler Public Improvement Authority Agenda Regular Meeting March 30, 2026 (Agenda)

Dynalectric Company's other public contracts

More Windler Public Improvement Authority contracts

Questions about this contract

Who was awarded the construction contract by Windler Public Improvement Authority?

Dynalectric Company was awarded this construction contract by Windler Public Improvement Authority, as recorded on March 30, 2026.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in Windler Public Improvement Authority Agenda Regular Meeting March 30, 2026 (Agenda), dated March 30, 2026 from Windler Public Improvement Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Dynalectric Company hold?

Dynalectric Company may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

Show 1 more question

What is Windler Public Improvement Authority currently buying?

Explore Windler Public Improvement Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →