District Recommends Hill Mechanical Data Center Upgrade
- Disclosed value
- Not to exceed $294,956
- From staffreport
- Document date
- Nov 12, 2026
The 30-second brief
High School District 214 recommends approving Hill Mechanical Services to replace the Forest View Educational Center’s Liebert cooling equipment and UPS system for a total cost not to exceed $294,956. The project will be procured through NCPA Cooperative Purchasing Contract 02-125, with installation targeted for summer 2027 and a one-year parts and labor warranty.
Hill Mechanical Services holds this equipment contract with Township HSD 214. Its other public contracts on record include work for Reavis Twp HSD 220 and WILMETTE PUBLIC LIBRARY DISTRICT.
Term as filed: Approximately 30-week equipment lead time; installation targeted for summer 2027; one-year parts and labor warranty.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Equipment
- Amount
- Not to exceed $294,956
- Document date
- November 12, 2026
- Term
- Approximately 30-week equipment lead time; installation targeted for summer 2027; one-year parts and labor warranty
- Vendor
- Hill Mechanical Services
- Agency
- Township HSD 214
- Source document
- High School District 214 StaffReport Approval of Forest View Network Center Liebert Unit 2026-11-12 (StaffReport)
Hill Mechanical Services's other public contracts
More Township HSD 214 contracts
Questions about this contract
Who was awarded the equipment contract by Township HSD 214?
Hill Mechanical Services was awarded this equipment contract by Township HSD 214, as recorded on November 12, 2026. The contract value is Not to exceed $294,956.
How much is the Hill Mechanical Services contract with Township HSD 214 worth?
The Hill Mechanical Services contract with Township HSD 214 is valued at Not to exceed $294,956, covering equipment work.
What type of contract is this?
This is a Equipment contract, documented as a staffreport record, structured as a not-to-exceed (ceiling) agreement.
Where was this contract approved?
This contract appears in High School District 214 StaffReport Approval of Forest View Network Center Liebert Unit 2026-11-12 (StaffReport), dated November 12, 2026 from Township HSD 214. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Hill Mechanical Services hold?
Hill Mechanical Services may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Township HSD 214 currently buying?
Explore Township HSD 214's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.