Final Retainage Release Recommended to Treto Construction
- Disclosed value
- $15,526.50 (final retainage release); total contract $314,180.00, total earned $310,530.00
- From agendapacket
- Document date
- Nov 9, 2026
The 30-second brief
WLC Engineering recommended that the Town of Evansville release $15,526.50 in retainage to Treto Construction, LLC as final payment on the Lathrop Road Pathway Phase 2 contract. The $314,180.00 contract is effectively complete with $310,530.00 earned and prior payments of $295,003.50.
Treto Construction LLC holds this construction contract with Town of Evansville. Its other public contracts on record include work for City of Casper and Converse County.
Term as filed: Final payment under contract for Evansville Lathrop Pathway Project Phase 2 through September 22, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $15,526.50 (final retainage release); total contract $314,180.00, total earned $310,530.00
- Document date
- November 9, 2026
- Term
- Final payment under contract for Evansville Lathrop Pathway Project Phase 2 through September 22, 2026
- Vendor
- Treto Construction LLC
- Agency
- Town of Evansville
- Source document
- Town of Evansville AgendaPacket Town Council Meeting 2026-11-09 (AgendaPacket)
Treto Construction LLC's other public contracts
More Town of Evansville contracts
Questions about this contract
Who was awarded the construction contract by Town of Evansville?
Treto Construction LLC was awarded this construction contract by Town of Evansville, as recorded on November 9, 2026. The contract value is $15,526.50 (final retainage release); total contract $314,180.00, total earned $310,530.00.
How much is the Treto Construction LLC contract with Town of Evansville worth?
The Treto Construction LLC contract with Town of Evansville is valued at $15,526.50 (final retainage release); total contract $314,180.00, total earned $310,530.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Town of Evansville AgendaPacket Town Council Meeting 2026-11-09 (AgendaPacket), dated November 9, 2026 from Town of Evansville. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Treto Construction LLC hold?
Treto Construction LLC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Town of Evansville currently buying?
Explore Town of Evansville's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.