CONTRACTAMENDED

Duininck Road Contract Change Order Decreases Amount

South Dakota Department of Transportation | All other boards
Disclosed value
$ (323,305.06) change on CCO No. 8; original contract amount $10,389,694.55
From report
Document date
Oct 2, 2026

The 30-second brief

What it covers

The South Dakota Department of Transportation processed Construction Change Order No. 8 for Duininck, Inc. The change decreased the $10,389,694.55 roadway contract by $323,305.06 because of project variations and removed unnecessary items.

Who holds it

Duininck Inc holds this construction contract with South Dakota Department of Transportation | All other boards. Its other public contracts on record include work for Pine County and Jackson County Drainage Authority.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$ (323,305.06) change on CCO No. 8; original contract amount $10,389,694.55
Document date
October 2, 2026
Source document
South Dakota Department of Transportation Report Construction Change Orders Report 2026-10-02 (Report)

Duininck Inc's other public contracts

More South Dakota Department of Transportation | All other boards contracts

Questions about this contract

Who was awarded the construction contract by South Dakota Department of Transportation | All other boards?

Duininck Inc was awarded this construction contract by South Dakota Department of Transportation | All other boards, as recorded on October 2, 2026. The contract value is $ (323,305.06) change on CCO No. 8; original contract amount $10,389,694.55.

How much is the Duininck Inc contract with South Dakota Department of Transportation | All other boards worth?

The Duininck Inc contract with South Dakota Department of Transportation | All other boards is valued at $ (323,305.06) change on CCO No. 8; original contract amount $10,389,694.55, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in South Dakota Department of Transportation Report Construction Change Orders Report 2026-10-02 (Report), dated October 2, 2026 from South Dakota Department of Transportation | All other boards. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Duininck Inc hold?

Duininck Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is South Dakota Department of Transportation | All other boards currently buying?