Muddy Creek WWTP building contract reduced via credit change order
- Disclosed value
- ($5,798.00) (Change Order No. 6 credit); final contract amount $1,792,708.00
- From agenda
- Document date
- Aug 26, 2026
The 30-second brief
NTMWD will approve a $5,798 credit change order on its Muddy Creek WWTP operations building contract with Eagle Contracting LLC, setting the final contract value at $1.79 million. The project is substantially complete and will proceed to final payment upon resolution of minor items.
Eagle Contracting LLC holds this construction contract with North Texas Municipal Water District. Its other public contracts on record include work for Texas Trinity River Authority | State of Texas and HARRIS COUNTY WCID 36.
Term as filed: Substantial completion September 7, 2026; final completion November 6, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- ($5,798.00) (Change Order No. 6 credit); final contract amount $1,792,708.00
- Document date
- August 26, 2026
- Term
- Substantial completion September 7, 2026; final completion November 6, 2026
- Vendor
- Eagle Contracting LLC
- Source document
- North Texas Municipal Water District Board of Directors Agenda 2026-08-27 (Agenda)
Eagle Contracting LLC's other public contracts
More North Texas Municipal Water District contracts
Questions about this contract
Who was awarded the construction contract by North Texas Municipal Water District?
Eagle Contracting LLC was awarded this construction contract by North Texas Municipal Water District, as recorded on August 26, 2026. The contract value is ($5,798.00) (Change Order No. 6 credit); final contract amount $1,792,708.00.
How much is the Eagle Contracting LLC contract with North Texas Municipal Water District worth?
The Eagle Contracting LLC contract with North Texas Municipal Water District is valued at ($5,798.00) (Change Order No. 6 credit); final contract amount $1,792,708.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in North Texas Municipal Water District Board of Directors Agenda 2026-08-27 (Agenda), dated August 26, 2026 from North Texas Municipal Water District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Eagle Contracting LLC hold?
Eagle Contracting LLC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is North Texas Municipal Water District currently buying?
Explore North Texas Municipal Water District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.