MBN BOOST 82 Westheimer Work Advances
- Disclosed value
- $5,248,888
- From agendapacket
- Document date
- Aug 19, 2026
- Term
- Substantial completion: April 2027
- Renews
- Free account
The 30-second brief
METRO reported that MBN’s BOOST 82 / Westheimer Segment 2 construction contract is underway. The $5,248,888 contract was 19% complete as of July 17, 2026, with substantial completion scheduled for April 2027.
MBN holds this construction contract with Metropolitan Transit Authority Of Harris County, Texas. Its other public contracts on record include work for City of Stockton and Harris Co Mta Non-Union Pension Plan.
The renewal date is on record. Get free alerts for pre-RFPs like this one, matched to what you sell.
Get pre-RFPs for work like this before the bid is out.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $5,248,888
- Document date
- August 19, 2026
- Term
- Substantial completion: April 2027
- Renews
- On record
- Vendor
- MBN
- Source document
- Metropolitan Transit Authority of Harris County AgendaPacket Infrastructure and Mobility Planning Committee Meeting 2026-08-19 (AgendaPacket)
MBN's other public contracts
More Metropolitan Transit Authority Of Harris County, Texas contracts
Questions about this contract
Who was awarded the construction contract by Metropolitan Transit Authority Of Harris County, Texas?
MBN was awarded this construction contract by Metropolitan Transit Authority Of Harris County, Texas, as recorded on August 19, 2026. The contract value is $5,248,888.
How much is the MBN contract with Metropolitan Transit Authority Of Harris County, Texas worth?
The MBN contract with Metropolitan Transit Authority Of Harris County, Texas is valued at $5,248,888, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Metropolitan Transit Authority of Harris County AgendaPacket Infrastructure and Mobility Planning Committee Meeting 2026-08-19 (AgendaPacket), dated August 19, 2026 from Metropolitan Transit Authority Of Harris County, Texas. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does MBN hold?
MBN may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Metropolitan Transit Authority Of Harris County, Texas currently buying?
Explore Metropolitan Transit Authority Of Harris County, Texas's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.