CONTRACTAMENDED

Lely High School Cooling Tower Contract Amended

Immokalee Technical College logoImmokalee Technical College
Disclosed value
$231,000.00 change order; original contract amount $3,594,708.00; revised contract amount $3,825,708.00
From staffreport
Document date
Nov 7, 2026
Term
Contract dated July 31, 2024

The 30-second brief

What it covers

The District School Board of Collier County approved a $231,000.00 change order for Charles Perry Partners, Inc. to replace the Lely High School cooling tower, structural support, and chiller. The amendment increases the Guaranteed Maximum Price from $3,594,708.00 to $3,825,708.00.

Who holds it

Charles Perry Partners Inc holds this construction contract with Immokalee Technical College. Its other public contracts on record include work for Orange Technical College-Mid Florida Campus.

What happens next

Term as filed: Contract dated July 31, 2024.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$231,000.00 change order; original contract amount $3,594,708.00; revised contract amount $3,825,708.00
Document date
November 7, 2026
Term
Contract dated July 31, 2024
Source document
The District School Board of Collier County StaffReport GMP Summary Lely High School Cooling Tower 2026-11-11 (StaffReport)

Charles Perry Partners Inc's other public contracts

More Immokalee Technical College contracts

Questions about this contract

Who was awarded the construction contract by Immokalee Technical College?

Charles Perry Partners Inc was awarded this construction contract by Immokalee Technical College, as recorded on November 7, 2026. The contract value is $231,000.00 change order; original contract amount $3,594,708.00; revised contract amount $3,825,708.00.

How much is the Charles Perry Partners Inc contract with Immokalee Technical College worth?

The Charles Perry Partners Inc contract with Immokalee Technical College is valued at $231,000.00 change order; original contract amount $3,594,708.00; revised contract amount $3,825,708.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in The District School Board of Collier County StaffReport GMP Summary Lely High School Cooling Tower 2026-11-11 (StaffReport), dated November 7, 2026 from Immokalee Technical College. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Charles Perry Partners Inc hold?

Charles Perry Partners Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Immokalee Technical College currently buying?

Explore Immokalee Technical College's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →