IWRB funds Raft River ESPA pipeline project

The Idaho Water Resource Board has committed $21M toward Raft River Irrigation District’s $49M Raft River Pipeline project to deliver Snake River water and reduce groundwater pumping impacts on the ESPA. Design is slated to finish in 2026, with construction expected from October 2026 to March 2030.

Document date · August 17, 2026

Track Idaho Deparment of Water Resources contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Idaho Deparment of Water Resources.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$49M total project cost; $21M IWRB obligated (included in ESPA RWS Program)
Contract type
FACILITIES
Contract term
Design completion estimated summer 2026; construction October 2026–March 2030
Renewal date
2030-03-31
Renewal
Capital project with planned construction completion by March 2030; no renewal terms specified.
Document type
Report
Source document
Idaho Water Resource Board Regional Water Sustainability Priority List 2026-08-17

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the facilities contract by Idaho Deparment of Water Resources?

Raft River Irr Dist was awarded this facilities contract by Idaho Deparment of Water Resources, as recorded on August 17, 2026. The contract value is $49M total project cost; $21M IWRB obligated (included in ESPA RWS Program).

How much is the Raft River Irr Dist contract with Idaho Deparment of Water Resources worth?

The Raft River Irr Dist contract with Idaho Deparment of Water Resources is valued at $49M total project cost; $21M IWRB obligated (included in ESPA RWS Program), covering facilities work.

What type of contract is this?

This is a Facilities contract, documented as a report record.

Where was this contract approved?

This contract appears in Idaho Water Resource Board Regional Water Sustainability Priority List 2026-08-17 (Report), dated August 17, 2026 from Idaho Deparment of Water Resources. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Raft River Irr Dist hold?

Raft River Irr Dist may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Raft River Irr Dist's profile

What is Idaho Deparment of Water Resources currently buying?

Explore Idaho Deparment of Water Resources's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Idaho Deparment of Water Resources's profile