CONTRACTAMENDED

Sherman WTP LAS & Rapid Mix project with Red River completed

Greater Texoma Utility Authority logoGreater Texoma Utility Authority
Disclosed value
$4,878,785.52 (final after -$19,099.67 change order)
From agendapacket
Document date
Jun 15, 2026

The 30-second brief

What it covers

GTUA accepted Red River Construction’s contract for the City of Sherman WTP-LAS & Rapid Mix Improvements Project as complete and approved Change Order No. 2, setting the final contract price at $4,878,785.52 after a $19,099.67 reduction.

Who holds it

Red River Construction holds this construction contract with Greater Texoma Utility Authority.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$4,878,785.52 (final after -$19,099.67 change order)
Document date
June 15, 2026
Source document
Greater Texoma Utility Authority Agenda Packet 2026-06-15 (AgendaPacket)

Red River Construction's other public contracts

More Greater Texoma Utility Authority contracts

Questions about this contract

Who was awarded the construction contract by Greater Texoma Utility Authority?

Red River Construction was awarded this construction contract by Greater Texoma Utility Authority, as recorded on June 15, 2026. The contract value is $4,878,785.52 (final after -$19,099.67 change order).

How much is the Red River Construction contract with Greater Texoma Utility Authority worth?

The Red River Construction contract with Greater Texoma Utility Authority is valued at $4,878,785.52 (final after -$19,099.67 change order), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Greater Texoma Utility Authority Agenda Packet 2026-06-15 (AgendaPacket), dated June 15, 2026 from Greater Texoma Utility Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Red River Construction hold?

Red River Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Greater Texoma Utility Authority currently buying?

Explore Greater Texoma Utility Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.