WWTP Electrical Contract Amended With Clista Electric
Hampton Shaler Water AuthorityUtility District · Allison Park, PA- Disclosed value
- $16,380 (Change Order 44); $8,896 (Change Order 45); $45,000 (Change Order 49)
- From minutes
- Document date
- Feb 25, 2026
The 30-second brief
Hampton Township Council approved three change orders totaling $70,276 with Clista Electric for the Wastewater Treatment Plant Project. The amendments cover trailer power/data, feeder conduits for relocation, and additional equipment and tools needed beyond the original contract end date.
Clista Electric holds this construction contract with Hampton Shaler Water Authority. Its other public contracts on record include work for Town of Allison and Town of Hampton.
Hear about the next contract at Hampton Shaler Water Authority early.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $16,380 (Change Order 44); $8,896 (Change Order 45); $45,000 (Change Order 49)
- Document date
- February 25, 2026
- Vendor
- Clista Electric
- Source document
- Hampton Township Council Meeting Minutes February 2026 (Minutes)
Clista Electric's other public contracts
More Hampton Shaler Water Authority contracts
Questions about this contract
Who was awarded the construction contract by Hampton Shaler Water Authority?
Clista Electric was awarded this construction contract by Hampton Shaler Water Authority, as recorded on February 25, 2026. The contract value is $16,380 (Change Order 44); $8,896 (Change Order 45); $45,000 (Change Order 49).
How much is the Clista Electric contract with Hampton Shaler Water Authority worth?
The Clista Electric contract with Hampton Shaler Water Authority is valued at $16,380 (Change Order 44); $8,896 (Change Order 45); $45,000 (Change Order 49), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Hampton Township Council Meeting Minutes February 2026 (Minutes), dated February 25, 2026 from Hampton Shaler Water Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Clista Electric hold?
Clista Electric may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Hampton Shaler Water Authority currently buying?
Explore Hampton Shaler Water Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.