Committee Reviews Kiewit Wastewater GMP Proposal
- Disclosed value
- Approximately $467 million proposed total, consisting of $343 million for competitive trade and equipment packages, $29.5 million for non-competitive site services and general conditions, approximately $36 million for construction-phase staff costs, $20 million proposed contingency, and $37.5 million CMAR fee
- From minutes
- Document date
- Jul 9, 2026
- Renews
- Free account
The 30-second brief
The Committee reviewed Kiewit's proposed approximately $467 million Guaranteed Maximum Price for WWTP Phase 1 and found it significantly above budget. Members recommended bidding the project as one package, with the City Council scheduled to consider the GMP on July 20, 2026.
KIEWIT holds this construction contract with City of Sioux. Its other public contracts on record include work for West Basin Municipal Water District and Kroenke Sports And Entertainment Metropolitan District 2.
The renewal date is on record. Get free alerts for pre-RFPs like this one, matched to what you sell.
Get pre-RFPs for work like this before the bid is out.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Approximately $467 million proposed total, consisting of $343 million for competitive trade and equipment packages, $29.5 million for non-competitive site services and general conditions, approximately $36 million for construction-phase staff costs, $20 million proposed contingency, and $37.5 million CMAR fee
- Document date
- July 9, 2026
- Term
- Project completion required by December 31, 2031
- Renews
- On record
- Vendor
- KIEWIT
- Agency
- City of Sioux
- Source document
- Sioux City Minutes Wastewater Treatment Plant Reconstruction and Design Advisory Committee Meeting 2026-07-09 (Minutes)
KIEWIT's other public contracts
More City of Sioux contracts
Questions about this contract
Who was awarded the construction contract by City of Sioux?
KIEWIT was awarded this construction contract by City of Sioux, as recorded on July 9, 2026. The contract value is Approximately $467 million proposed total, consisting of $343 million for competitive trade and equipment packages, $29.5 million for non-competitive site services and general conditions, approximately $36 million for construction-phase staff costs, $20 million proposed contingency, and $37.5 million CMAR fee.
How much is the KIEWIT contract with City of Sioux worth?
The KIEWIT contract with City of Sioux is valued at Approximately $467 million proposed total, consisting of $343 million for competitive trade and equipment packages, $29.5 million for non-competitive site services and general conditions, approximately $36 million for construction-phase staff costs, $20 million proposed contingency, and $37.5 million CMAR fee, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Sioux City Minutes Wastewater Treatment Plant Reconstruction and Design Advisory Committee Meeting 2026-07-09 (Minutes), dated July 9, 2026 from City of Sioux. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does KIEWIT hold?
KIEWIT may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Sioux currently buying?