Omak Recommends SCADA Upgrade Change Order
City of OmakCity · Omak, WA- Disclosed value
- $43,510.77 increase; revised contract amount $382,010.77 from original $338,500.00
- From agendapacket
- Document date
- Nov 2, 2026
The 30-second brief
The City of Omak recommends a $43,510.77 change order with Service Electric Co., Inc. for its SCADA Upgrade Project. The work replaces a 600-amp feeder breaker and an influent pump variable frequency drive, raises the contract total to $382,010.77, and adds two working days to each completion milestone.
Service Electric Company Inc holds this construction contract with City of Omak. Its other public contracts on record include work for City of Snohomish and City of Marysville.
Term as filed: Substantial completion: 64 working days; physical completion: 69 working days, each increased by 2 working days.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $43,510.77 increase; revised contract amount $382,010.77 from original $338,500.00
- Document date
- November 2, 2026
- Term
- Substantial completion: 64 working days; physical completion: 69 working days, each increased by 2 working days
- Agency
- City of Omak
- Source document
- Omak City Council AgendaPacket 2026-11-02 (AgendaPacket)
Service Electric Company Inc's other public contracts
More City of Omak contracts
Questions about this contract
Who was awarded the construction contract by City of Omak?
Service Electric Company Inc was awarded this construction contract by City of Omak, as recorded on November 2, 2026. The contract value is $43,510.77 increase; revised contract amount $382,010.77 from original $338,500.00.
How much is the Service Electric Company Inc contract with City of Omak worth?
The Service Electric Company Inc contract with City of Omak is valued at $43,510.77 increase; revised contract amount $382,010.77 from original $338,500.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Omak City Council AgendaPacket 2026-11-02 (AgendaPacket), dated November 2, 2026 from City of Omak. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Service Electric Company Inc hold?
Service Electric Company Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Omak currently buying?
Explore City of Omak's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.