P. Gioioso Installs MWRA Water Main on Ward Street
- Document date
- Aug 3, 2026
The 30-second brief
Newton DPW and MWRA are working with P. Gioioso on water main installation along Ward Street between Waverley Avenue and Centre Street the week of August 3–7, 2026, with related work planned on Centre and Grafton Streets. The project will involve lane closures and utility upgrades.
P. Gioioso holds this construction contract with City of Newton. Its other public contracts on record include work for City of Cambridge.
Term as filed: Week of August 3–7, 2026 and upcoming Summer 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- August 3, 2026
- Term
- Week of August 3–7, 2026 and upcoming Summer 2026
- Vendor
- P. Gioioso
- Agency
- City of Newton
- Source document
- City of Newton DPW Weekly Construction Schedule 2026-08-03 (Report)
P. Gioioso's other public contracts
More City of Newton contracts
Questions about this contract
Who was awarded the construction contract by City of Newton?
P. Gioioso was awarded this construction contract by City of Newton, as recorded on August 3, 2026.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in City of Newton DPW Weekly Construction Schedule 2026-08-03 (Report), dated August 3, 2026 from City of Newton. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What is City of Newton currently buying?
Explore City of Newton's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.