Bill Bruce Builders Continues Monticello Wastewater Plant Project
- Disclosed value
- $23,448,000 original contract; $24,546,256.81 before Change Order #9
- From agendapacket
- Document date
- Nov 2, 2026
- Renews
- Free account
The 30-second brief
Bill Bruce Builders, Inc. is performing Monticello’s $23.448 million Wastewater Treatment Plant Improvements contract. Approved change orders have increased the contract to at least $24.546 million before the latest amendment, with completion scheduled for March 2027.
Bill Bruce Builders Inc holds this construction contract with City of Monticello. Its other public contracts on record include work for City of Le Claire.
The renewal date is on record. Get free alerts for pre-RFPs like this one, matched to what you sell.
Get pre-RFPs for work like this before the bid is out.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $23,448,000 original contract; $24,546,256.81 before Change Order #9
- Document date
- November 2, 2026
- Term
- Original substantial completion September 26, 2026; current substantial completion March 16, 2027; final payment April 9, 2027
- Renews
- On record
- Vendor
- Bill Bruce Builders Inc
- Agency
- City of Monticello
- Source document
- City of Monticello AgendaPacket City Council Meeting 2026-11-02 (AgendaPacket)
Bill Bruce Builders Inc's other public contracts
More City of Monticello contracts
Questions about this contract
Who was awarded the construction contract by City of Monticello?
Bill Bruce Builders Inc was awarded this construction contract by City of Monticello, as recorded on November 2, 2026. The contract value is $23,448,000 original contract; $24,546,256.81 before Change Order #9.
How much is the Bill Bruce Builders Inc contract with City of Monticello worth?
The Bill Bruce Builders Inc contract with City of Monticello is valued at $23,448,000 original contract; $24,546,256.81 before Change Order #9, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in City of Monticello AgendaPacket City Council Meeting 2026-11-02 (AgendaPacket), dated November 2, 2026 from City of Monticello. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Bill Bruce Builders Inc hold?
Bill Bruce Builders Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Monticello currently buying?
Explore City of Monticello's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.