CONTRACTONGOING

MBI Continues Goddard Water Looping Project

City of Goddard
Document date
Nov 2, 2026

The 30-second brief

What it covers

MBI continued Goddard’s water-looping construction project and repaired leaks found during pressure testing. The project was 70 days into a 210-day contract as of October 19, 2026.

Who holds it

MBI holds this construction contract with City of Goddard. Its other public contracts on record include work for Nederland Fire Protection District and Town of Topsail Beach.

What happens next

Term as filed: Goddard Water Looping project: 70 of 210 contract days elapsed as of October 19, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Document date
November 2, 2026
Term
Goddard Water Looping project: 70 of 210 contract days elapsed as of October 19, 2026
Vendor
MBI
Source document
City of Goddard AgendaPacket 2026-11-02 (AgendaPacket)

MBI's other public contracts

More City of Goddard contracts

Questions about this contract

Who was awarded the construction contract by City of Goddard?

MBI was awarded this construction contract by City of Goddard, as recorded on November 2, 2026.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in City of Goddard AgendaPacket 2026-11-02 (AgendaPacket), dated November 2, 2026 from City of Goddard. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does MBI hold?

MBI may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

Show 1 more question

What is City of Goddard currently buying?

Explore City of Goddard's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →