CONTRACTAPPROVED

City of Fort Dodge Awards Construction Contract to Cardenas Concrete (November 2026)

City of Fort Dodge logoCity of Fort Dodge
Disclosed value
Change Order #2: $5,840.80; Sub-Final Pay Estimate #6: $15,189.23; revised contract price: $218,409.49
From agenda
Approved
Nov 6, 2026
Term
Estimated completion date July 10, 2026

The 30-second brief

What it covers

Fort Dodge approved a $5,840.80 change order and $15,189.23 sub-final pay estimate for Cardenas Concrete’s 2026 PCC Patch Street Repair Project. The change brings the revised contract price to $218,409.49 as the city closes out the completed work.

Who holds it

Cardenas Concrete holds this construction contract with City of Fort Dodge. Its other public contracts on record include work for City of Jefferson.

What happens next

Term as filed: Estimated completion date July 10, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Change Order #2: $5,840.80; Sub-Final Pay Estimate #6: $15,189.23; revised contract price: $218,409.49
Document date
November 6, 2026
Term
Estimated completion date July 10, 2026
Source document
City of Fort Dodge Agenda 2026-11-09 (Agenda)

Cardenas Concrete's other public contracts

More City of Fort Dodge contracts

Questions about this contract

Who was awarded the construction contract by City of Fort Dodge?

Cardenas Concrete was awarded this construction contract by City of Fort Dodge, as recorded on November 6, 2026. The contract value is Change Order #2: $5,840.80; Sub-Final Pay Estimate #6: $15,189.23; revised contract price: $218,409.49.

How much is the Cardenas Concrete contract with City of Fort Dodge worth?

The Cardenas Concrete contract with City of Fort Dodge is valued at Change Order #2: $5,840.80; Sub-Final Pay Estimate #6: $15,189.23; revised contract price: $218,409.49, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in City of Fort Dodge Agenda 2026-11-09 (Agenda), dated November 6, 2026 from City of Fort Dodge. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Cardenas Concrete hold?

Cardenas Concrete may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is City of Fort Dodge currently buying?

Explore City of Fort Dodge's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →