Garney Construction Wins $28.6 Million Well Project

City of College Station logoCity of College Station
Disclosed value
GMP $27,886,767.07; City contingency $697,169.18; total appropriation $28,583,936.25
From minutes
Document date
Mar 26, 2026
Renews
Free account

The 30-second brief

What it covers

College Station amended its CMAR contract with Garney Construction., Inc. to accept a $27.89 million GMP for the Wells 10, 11 and 12 Project. Including a $697,169.18 contingency, the total appropriation is $28,583,936.25, with completion planned before August 2028.

Who holds it

Garney Construction Inc holds this construction contract with City of College Station. Its other public contracts on record include work for City of Siloam Springs.

What happens next

The renewal date is on record. A free account shows it, with the renewals for every City of College Station contract.

Renewal date on recordLocked

Know when this contract comes back up.

See the renewal date

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
GMP $27,886,767.07; City contingency $697,169.18; total appropriation $28,583,936.25
Document date
March 26, 2026
Term
Construction began early 2025; completion slated before August 2028
Renews
Free account
Source document
City of College Station Minutes City Council Meeting March 26, 2026 (Minutes)

Garney Construction Inc's other public contracts

More City of College Station contracts

Questions about this contract

Who was awarded the construction contract by City of College Station?

Garney Construction Inc was awarded this construction contract by City of College Station, as recorded on March 26, 2026. The contract value is GMP $27,886,767.07; City contingency $697,169.18; total appropriation $28,583,936.25.

How much is the Garney Construction Inc contract with City of College Station worth?

The Garney Construction Inc contract with City of College Station is valued at GMP $27,886,767.07; City contingency $697,169.18; total appropriation $28,583,936.25, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in City of College Station Minutes City Council Meeting March 26, 2026 (Minutes), dated March 26, 2026 from City of College Station. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Garney Construction Inc hold?

Garney Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is City of College Station currently buying?

Explore City of College Station's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →