Chesterfield Recommends $47.6 Million Interchange Agreement
- Disclosed value
- Estimated total project cost $47,568,000; Commission funding not to exceed $14,247,000; City responsibility estimated at $33,321,000
- From agendapacket
- Document date
- Nov 2, 2026
- Renews
- Free account
The 30-second brief
Chesterfield recommended a cost-share agreement with the Missouri Highways and Transportation Commission for the $47.568 million I-64 and Long Road Interchange project. The Commission would provide up to $14.247 million and manage project letting and inspection, while the city would fund the remaining estimated costs.
Missouri Highways & Transportation Commission holds this contract with City of Chesterfield. Its other public contracts on record include work for City of Osage Beach city and City of Hannibal.
The renewal date is on record. Get free alerts for pre-RFPs like this one, matched to what you sell.
Get pre-RFPs for work like this before the bid is out.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Amount
- Estimated total project cost $47,568,000; Commission funding not to exceed $14,247,000; City responsibility estimated at $33,321,000
- Document date
- November 2, 2026
- Term
- Agreement supports construction anticipated to commence in 2029 and be completed by 2030
- Renews
- On record
- Agency
- City of Chesterfield
- Source document
- City of Chesterfield AgendaPacket 2026-11-02 (AgendaPacket)
Missouri Highways & Transportation Commission's other public contracts
More City of Chesterfield contracts
Questions about this contract
Who was awarded the government contract by City of Chesterfield?
Missouri Highways & Transportation Commission was awarded this government contract by City of Chesterfield, as recorded on November 2, 2026. The contract value is Estimated total project cost $47,568,000; Commission funding not to exceed $14,247,000; City responsibility estimated at $33,321,000.
How much is the Missouri Highways & Transportation Commission contract with City of Chesterfield worth?
The Missouri Highways & Transportation Commission contract with City of Chesterfield is valued at Estimated total project cost $47,568,000; Commission funding not to exceed $14,247,000; City responsibility estimated at $33,321,000.
What type of contract is this?
This is a government contract, documented as a agendapacket record, structured as a not-to-exceed (ceiling) agreement.
Where was this contract approved?
This contract appears in City of Chesterfield AgendaPacket 2026-11-02 (AgendaPacket), dated November 2, 2026 from City of Chesterfield. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Missouri Highways & Transportation Commission hold?
Missouri Highways & Transportation Commission may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Chesterfield currently buying?
Explore City of Chesterfield's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.