CVSan Accepts Completion of DL Falk Building Project
Castro Valley Sanitary DistrictSpecial District · Castro Valley, CA- Disclosed value
- $23,746,569.57 total project cost; $2,902,569.57 total change orders
- From agenda
- Document date
- Jul 7, 2026
The 30-second brief
Castro Valley Sanitary District accepted completion of the Operations and Engineering Building Project constructed by DL Falk Construction Inc. The project cost totaled $23.75 million, including $2.90 million in change orders.
Dl Falk Construction Inc holds this construction contract with Castro Valley Sanitary District. Its other public contracts on record include work for Laney College.
Term as filed: Substantially completed October 21, 2025, within 670 working days.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $23,746,569.57 total project cost; $2,902,569.57 total change orders
- Document date
- July 7, 2026
- Term
- Substantially completed October 21, 2025, within 670 working days
- Vendor
- Dl Falk Construction Inc
- Source document
- Castro Valley Sanitary District Agenda 2026-07-07 (Agenda)
Dl Falk Construction Inc's other public contracts
More Castro Valley Sanitary District contracts
Questions about this contract
Who was awarded the construction contract by Castro Valley Sanitary District?
Dl Falk Construction Inc was awarded this construction contract by Castro Valley Sanitary District, as recorded on July 7, 2026. The contract value is $23,746,569.57 total project cost; $2,902,569.57 total change orders.
How much is the Dl Falk Construction Inc contract with Castro Valley Sanitary District worth?
The Dl Falk Construction Inc contract with Castro Valley Sanitary District is valued at $23,746,569.57 total project cost; $2,902,569.57 total change orders, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in Castro Valley Sanitary District Agenda 2026-07-07 (Agenda), dated July 7, 2026 from Castro Valley Sanitary District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Dl Falk Construction Inc hold?
Dl Falk Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Castro Valley Sanitary District currently buying?
Explore Castro Valley Sanitary District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.