CONTRACTAMENDED

Authority Approves Kukurin Manhole Change Order

Blair Township Water Sewer Authority
Disclosed value
$2,267.19 change order; $242,927.53 payment with 30% withheld; $363,636 due next month
From minutes
Document date
Aug 5, 2026

The 30-second brief

What it covers

Blair Township Water and Sewer Authority approved a $2,267.19 change order for Kukurin contracting. The additional work involves the Hollidaysburg manhole and falls outside the original project scope.

Who holds it

Kukurin Contracting holds this construction contract with Blair Township Water Sewer Authority. Its other public contracts on record include work for College Township Water Authority and Borough of Indiana.

Hear about the next contract at Blair Township Water Sewer Authority early.

Get pre-RFP alerts free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$2,267.19 change order; $242,927.53 payment with 30% withheld; $363,636 due next month
Document date
August 5, 2026
Source document
Blair Township Water and Sewer Authority Minutes Regular Meeting August 5, 2026 (Minutes)

Kukurin Contracting's other public contracts

More Blair Township Water Sewer Authority contracts

Questions about this contract

Who was awarded the construction contract by Blair Township Water Sewer Authority?

Kukurin Contracting was awarded this construction contract by Blair Township Water Sewer Authority, as recorded on August 5, 2026. The contract value is $2,267.19 change order; $242,927.53 payment with 30% withheld; $363,636 due next month.

How much is the Kukurin Contracting contract with Blair Township Water Sewer Authority worth?

The Kukurin Contracting contract with Blair Township Water Sewer Authority is valued at $2,267.19 change order; $242,927.53 payment with 30% withheld; $363,636 due next month, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Blair Township Water and Sewer Authority Minutes Regular Meeting August 5, 2026 (Minutes), dated August 5, 2026 from Blair Township Water Sewer Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Kukurin Contracting hold?

Kukurin Contracting may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Blair Township Water Sewer Authority currently buying?

Explore Blair Township Water Sewer Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →