Kirby Electric Terminal Contract Change Order Approved
- Disclosed value
- Increased by $318,167.90, from $10,909,670.77 to $11,227,838.67
- From minutes
- Document date
- Jul 17, 2026
- Term
- Extended through September 30, 2026
The 30-second brief
The Allegheny County Airport Authority approved Change Order #10 with Kirby Electric, Inc. for new Terminal construction work. The change increases the contract by $318,167.90 to a cumulative $11,227,838.67 and extends the term through September 30, 2026.
Kirby Electric Inc holds this construction contract with Allegheny County Airport Authority. Its other public contracts on record include work for Allegheny County Sanitary Authority Pension Plan 2 and Allegheny County Sanitary Authority.
Term as filed: Extended through September 30, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Increased by $318,167.90, from $10,909,670.77 to $11,227,838.67
- Document date
- July 17, 2026
- Term
- Extended through September 30, 2026
- Vendor
- Kirby Electric Inc
- Source document
- Allegheny County Airport Authority Minutes Board Meeting 2026-07-17 (Minutes)
Kirby Electric Inc's other public contracts
More Allegheny County Airport Authority contracts
Questions about this contract
Who was awarded the construction contract by Allegheny County Airport Authority?
Kirby Electric Inc was awarded this construction contract by Allegheny County Airport Authority, as recorded on July 17, 2026. The contract value is Increased by $318,167.90, from $10,909,670.77 to $11,227,838.67.
How much is the Kirby Electric Inc contract with Allegheny County Airport Authority worth?
The Kirby Electric Inc contract with Allegheny County Airport Authority is valued at Increased by $318,167.90, from $10,909,670.77 to $11,227,838.67, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Allegheny County Airport Authority Minutes Board Meeting 2026-07-17 (Minutes), dated July 17, 2026 from Allegheny County Airport Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Kirby Electric Inc hold?
Kirby Electric Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Allegheny County Airport Authority currently buying?
Explore Allegheny County Airport Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.