Tooele City amends wells drilling contract for design changes
Trusted by teams at
Description
Tooele City Council is set to approve Change Order No. 3 with Hydro Resources Rocky Mountain, Inc. for the 2025 Tooele City Wells Project, adding $252,475.09 and authorizing an $85,000 contingency to modify the production well design and depth. The amendment keeps the substantial completion date of January 10, 2026 while enhancing well performance and reducing drilling risks.
Contract Details
Contract Amount
$252,475.09 (plus $85,000.00 contingency; new total contract price $2,830,765.59)
Vendor
HYDRO RESOURCES ROCKY MOUNTAIN INC
Agency
City of Tooele, UT
Contract Type
CONSTRUCTION
Document Date
April 1, 2026
Contract Term
Original substantial completion January 10, 2026; ready for final payment February 10, 2026 (unchanged by Change Order No. 3)
Renewal Date
2026-02-10
Renewal Info
Change Order No. 3 is the third amendment to the original July 2025 wells drilling contract, increasing the contract sum from $2,578,290.50 to $2,830,765.59 without extending the completion dates.
More from HYDRO RESOURCES ROCKY MOUNTAIN INC
More from City of Tooele
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.