Decatur Utilities Sanitary Sewer Mains Rehabilitation Pipe Bursting Method FY27 - Morgan
Decatur UtilitiesUtility District · Decatur, AL- Due
- Nov 19, 2026
- 12 days left
- Primary contact
- Garrett Bodine
- (256) 552-1487
The 30-second brief
Decatur Utilities is seeking bids for sanitary sewer mains rehabilitation using pipe bursting method and CIPP liner for FY27 in Morgan, AL. The project generally consists of rehabbing 8,325 LF of 8" vitrified clay, 2,800 LF of 10" vitrified clay, 2,700 LF of 12" vitrified clay, 2,700 LF of 8" CIPP liner, 1,000 LF of 10" CIPP liner, 2,500 LF of 12" CIPP liner, 100 LF of 15" CIPP liner, 100 LF of 18" CIPP liner, and 2,100 LF of 24" CIPP liner to HDPE via pipe bursting method. Additionally, the project includes 270 lateral service line replacements from the sewer main to the property line, various point repairs, and cold mix asphalt, concrete, and sod restoration. Submission deadline is November 19, 2026, at 02:00 PM.
8, 325 LF of 8" vitrified clay, 2, 800 LF of 10" vitrified clay, 2, 700 LF of 12" vitrified clay, 2, 700 LF of 8" CIPP liner, 1, 000 LF of 10" CIPP liner, 2, 500 LF of 12" CIPP liner, 100 LF of 15" CIPP liner, 100 LF of 18" CIPP liner, 2, 100 LF of 24" CIPP liner to HDPE via pipe bursting method, 270 lateral service line replacements, Point repairs, Cold mix asphalt restoration, Concrete restoration, Sod restoration
Bids like this start as pre-RFPs. Get the next ones early.
Get matched pre-RFPs freeFree account · 30-second setup · No credit card
Summary
Decatur Utilities is seeking bids for sanitary sewer mains rehabilitation using pipe bursting method and CIPP liner for FY27 in Morgan, AL. The project generally consists of rehabbing 8,325 LF of 8" vitrified clay, 2,800 LF of 10" vitrified clay, 2,700 LF of 12" vitrified clay, 2,700 LF of 8" CIPP liner, 1,000 LF of 10" CIPP liner, 2,500 LF of 12" CIPP liner, 100 LF of 15" CIPP liner, 100 LF of 18" CIPP liner, and 2,100 LF of 24" CIPP liner to HDPE via pipe bursting method.
Additionally, the project includes 270 lateral service line replacements from the sewer main to the property line, various point repairs, and cold mix asphalt, concrete, and sod restoration. Submission deadline is November 19, 2026, at 02:00 PM.
REQUIRED DELIVERABLES
8, 325 LF of 8" vitrified clay, 2, 800 LF of 10" vitrified clay, 2, 700 LF of 12" vitrified clay, 2, 700 LF of 8" CIPP liner, 1, 000 LF of 10" CIPP liner, 2, 500 LF of 12" CIPP liner, 100 LF of 15" CIPP liner, 100 LF of 18" CIPP liner, 2, 100 LF of 24" CIPP liner to HDPE via pipe bursting method, 270 lateral service line replacements, Point repairs, Cold mix asphalt restoration, Concrete restoration, Sod restoration
- Submit to
- 1002 Central Parkway SW PO Box 2232, Decatur, AL, 35601
- Scope location
- Morgan, AL
Questions about this BID
How do I respond to this Bid from Decatur Utilities?
Review the full solicitation document for submission requirements, evaluation criteria, and deadlines. The submission deadline is November 19, 2026. The solicitation specifies required deliverables that must be addressed in your response. Submissions should be delivered to: 1002 Central Parkway SW PO Box 2232, Decatur, AL, 35601. For questions, contact Garrett Bodine.
Can small businesses or minority-owned firms bid on this Bid?
Most government agencies, including Decatur Utilities in AL, encourage participation from small businesses, minority-owned, women-owned, and disadvantaged business enterprises (MBE/WBE/DBE). Check the full solicitation for any small business participation goals.
What happens after the Bid submission deadline?
After the deadline, the issuing agency reviews all submissions against the stated evaluation criteria. This typically includes a compliance check, technical evaluation, cost analysis, and may involve oral presentations with shortlisted vendors.
Can I ask questions about this solicitation before submitting?
Yes, most solicitations allow vendors to submit questions during a designated period. The primary contact is Garrett Bodine at (256) 552-1487. Questions and answers are typically shared with all prospective bidders.
What are the key deliverables?
The solicitation specifies the following deliverables: 8, 325 LF of 8" vitrified clay, 2, 800 LF of 10" vitrified clay, 2, 700 LF of 12" vitrified clay, 2, 700 LF of 8" CIPP liner, 1, 000 LF of 10" CIPP liner, 2, 500 LF of 12" CIPP liner, 100 LF of 15" CIPP liner, 100 LF of 18" CIPP liner, 2, 100 LF of 24" CIPP liner to HDPE via pipe bursting method, 27. Proposals should clearly address how each deliverable will be met.
Show 4 more questions
Where can I find more RFPs from Decatur Utilities?
All active and historical solicitations from Decatur Utilities are tracked and searchable. As a utility district agency, Decatur Utilities regularly publishes solicitations. Visit the agency profile to see current open bids, past contracts, vendor relationships, and decision-maker contacts.
Is this solicitation still open for submissions?
Based on the posted deadline of November 19, 2026, this solicitation appears to still be accepting submissions. Deadlines may change through amendments or addenda, so always verify the current status directly with the issuing agency before preparing your response.
What documents are required to bid on this Bid?
Requirements vary by solicitation, but common documents include a technical proposal, cost/price proposal, proof of insurance, relevant certifications, past performance references, and any forms specified in the solicitation. Review the full document from Decatur Utilities for the complete list.
What is the scope of this project?
This solicitation defines a specific project scope. The scope covers the following locations: Morgan, AL. Review the full solicitation for detailed scope requirements.