Brigham City - West Forest T-Line Drilled Pier Foundations RFP - 2026
- Due
- Jun 1, 2026
- Deadline passed
- Posted
- Apr 30, 2026
- Contract term
- 30 years
- Primary contact
- Kristina Rasmussen
- (435) 613-0700
The 30-second brief
Brigham City requests emailed proposals for the installation of three drilled pier foundations for the West Forest T-Line project located in Box Elder County, Utah. The scope includes site preparation, excavation, concrete placement with a minimum compressive strength of 4500 psi at 28 days, reinforcing steel, and anchor bolt installation per design specifications. Proposals are due by 3:00 p.m. on Monday, June 1, 2026, and must be submitted via email to Kristina Rasmussen. A mandatory pre-bid meeting will be held onsite on Wednesday, May 20, 2026, at 10:00 a.m. Questions should be directed via email to Troy Dahlgren no later than May 25, 2026. The required completion date for foundation installation is August 31, 2026, subject to a $250 per day late penalty.
CUSTOM POLE, 65FT CONCRETE PIER FOUNDATION, WEATHERING STEEL, STR WFS-1-DE; CUSTOM POLE, 80FT CONCRETE PIER FOUNDATION, WEATHERING STEEL, STR WFS-8-DE, WFS-13-DE
Price
Hear what Brigham plans next before it's posted.
Get alerts freeFree account · 30-second setup · No credit card
Summary
Brigham City requests emailed proposals for the installation of three drilled pier foundations for the West Forest T-Line project located in Box Elder County, Utah.
The scope includes site preparation, excavation, concrete placement with a minimum compressive strength of 4500 psi at 28 days, reinforcing steel, and anchor bolt installation per design specifications. Proposals are due by 3:00 p.m. on Monday, June 1, 2026, and must be submitted via email to Kristina Rasmussen. A mandatory pre-bid meeting will be held onsite on Wednesday, May 20, 2026, at 10:00 a.m. Questions should be directed via email to Troy Dahlgren no later than May 25, 2026. The required completion date for foundation installation is August 31, 2026, subject to a $250 per day late penalty.
EVALUATION CRITERIA
Price
REQUIRED DELIVERABLES
8- CUSTOM POLE
- 65FT CONCRETE PIER FOUNDATION
- WEATHERING STEEL
- STR WFS-1-DE; CUSTOM POLE
- 80FT CONCRETE PIER FOUNDATION
- WEATHERING STEEL
- STR WFS-8-DE
- WFS-13-DE
REQUIRED ATTACHMENTS
7- Bidding proposal
- Proposed manufacturing schedule
- Payment terms
- Warranties and guaranties
- Installation schedule
- Proposed slurry additive
- Slurry storage and disposal plan
- Submit to
- [email protected]
- Scope location
- Brigham City, UT
- Reported agency
- Brigham City
Questions about this RFP
How do I respond to this RFP from City of Brigham?
Review the full solicitation document for submission requirements, evaluation criteria, and deadlines. The submission deadline is June 1, 2026. The solicitation specifies required deliverables that must be addressed in your response. Be sure to include all required attachments as outlined in the solicitation. Submissions should be delivered to: [email protected]. For questions, contact Kristina Rasmussen.
Can small businesses or minority-owned firms bid on this RFP?
Most government agencies, including City of Brigham in UT, encourage participation from small businesses, minority-owned, women-owned, and disadvantaged business enterprises (MBE/WBE/DBE). Check the full solicitation for any small business participation goals.
What happens after the RFP submission deadline?
After the deadline, the issuing agency reviews all submissions against the stated evaluation criteria. This typically includes a compliance check, technical evaluation, cost analysis, and may involve oral presentations with shortlisted vendors.
Can I ask questions about this solicitation before submitting?
Yes, most solicitations allow vendors to submit questions during a designated period. The primary contact is Kristina Rasmussen at (435) 613-0700. Questions and answers are typically shared with all prospective bidders.
What are the key deliverables?
The solicitation specifies the following deliverables: CUSTOM POLE, 65FT CONCRETE PIER FOUNDATION, WEATHERING STEEL, STR WFS-1-DE; CUSTOM POLE, 80FT CONCRETE PIER FOUNDATION, WEATHERING STEEL, STR WFS-8-DE, WFS-13-DE. Proposals should clearly address how each deliverable will be met.
Show 5 more questions
What are the evaluation criteria for this solicitation?
This solicitation includes specific evaluation criteria that will be used to score proposals. The criteria include: "Price" Vendors should carefully align their proposals with each criterion to maximize their score.
Where can I find more RFPs from City of Brigham?
All active and historical solicitations from City of Brigham are tracked and searchable. As a city agency, City of Brigham regularly publishes solicitations. Visit the agency profile to see current open bids, past contracts, vendor relationships, and decision-maker contacts.
What is the contract term for this solicitation?
The anticipated contract term is 30 years. Contract terms may include renewal options.
What documents are required to bid on this RFP?
Requirements vary by solicitation, but common documents include a technical proposal, cost/price proposal, proof of insurance, relevant certifications, past performance references, and any forms specified in the solicitation. This solicitation specifically requires the following attachments: bidding proposal, proposed manufacturing schedule, payment terms, warranties and guaranties, installation schedule, proposed slurry additive, slurry storage and disposal plan. Review the full document from City of Brigham for the complete list.
What is the scope of this project?
This solicitation defines a specific project scope. The scope covers the following locations: Brigham City, UT. Review the full solicitation for detailed scope requirements.