Legacy lift station odor control changed
Galveston County Mud 82Texas- Detected
- Sep 10, 2026
- 48 days ago
- Sector
- Utilities
- Est. value
- Free account
See what it's worth and when it goes to bid.
See the estimated valueFree account · 30-second setup · No credit card
From the meeting
The minutes and attached change-order material show Peltier Brothers Construction and GFT Infrastructure, Inc. working on a decided lift station project that was amended for odor control. Change Order No.
15, and the proposal says the system lead time was 3-5 weeks for submittals and 13-15 weeks for equipment. This is a strong incumbent and integration signal.
- Meeting date
- September 10, 2026
- Agency
- Galveston County Mud 82
More from Galveston County Mud 82
Similar pre-RFPs forming now
Matching work at other agencies, before it reaches a bid portal.
Questions about this project
What is a pre-RFP?
A pre-RFP is an early indicator that a government agency is planning a purchase — a project discussed in a board meeting, a budget line item, a new hire, or a grant award — captured before a formal RFP or bid is published. Acting on pre-RFPs gives SLED and B2G vendors months of lead time to build relationships and shape requirements.
When will Galveston County Mud 82 issue an RFP for this project?
Pre-RFPs typically surface 6–18 months before a formal solicitation is published. Civic IQ tracks Galveston County Mud 82's meeting records, agendas, and budgets continuously and updates this pre-RFP as the project moves through the buying cycle toward an RFP.
How can vendors engage with Galveston County Mud 82 before the RFP is published?
Vendors who reach out during the planning window can help shape requirements and build relationships with the decision-makers running the project. A free Civic IQ account unlocks this pre-RFP's source document, forecasted RFP timing, and verified Galveston County Mud 82 decision-maker contacts.
Where can I find more utilities government opportunities in Texas?
Civic IQ monitors board meetings, agendas, budgets, and capital plans from 100,000+ state and local agencies and surfaces utilities pre-RFPs in Texas as soon as they appear — months before they reach bid portals.