Water system Contract A change order
City of SalemMissouri- Detected
- Jul 14, 2026
- 111 days ago
- Sector
- Capital Projects
- Est. value
- Free account
Get pre-RFPs like this one as they surface.
Get briefs like this freeFree account · 30-second setup · No credit card
THE 30-SECOND BRIEF
The Board approved Change Order No. 1 on July 14, 2026 for the Salem Water System Improvements – Contract A with BuildTec Construction. The change adds $34,736 for extra fire hydrants, valves, piping, and related pavement and landscape restoration, and extends the construction completion date to August 1, 2026. This shows an active capital project with BuildTec as general contractor and Archer-Elgin as engineer, pointing to follow-on construction, restoration, and utility work opportunities as the system expands.
This is a change order for an existing construction contract, adding fire hydrants and valves and extending time by 108 days.
From the meeting
- Meeting date
- July 14, 2026
- Agency
- City of Salem
More from City of Salem
Similar pre-RFPs forming now
Matching work at other agencies, before it reaches a bid portal.
Questions about this project
What is a pre-RFP?
A pre-RFP is an early indicator that a government agency is planning a purchase — a project discussed in a board meeting, a budget line item, a new hire, or a grant award — captured before a formal RFP or bid is published. Acting on pre-RFPs gives SLED and B2G vendors months of lead time to build relationships and shape requirements.
When will City of Salem issue an RFP for this project?
Pre-RFPs typically surface 6–18 months before a formal solicitation is published. Civic IQ tracks City of Salem's meeting records, agendas, and budgets continuously and updates this pre-RFP as the project moves through the buying cycle toward an RFP.
How can vendors engage with City of Salem before the RFP is published?
Vendors who reach out during the planning window can help shape requirements and build relationships with the decision-makers running the project. A free Civic IQ account sends you the pre-RFPs that fit what you sell, with the AI brief and the decision makers for the top matches in each digest.
Where can I find more capital projects government opportunities in Missouri?
Civic IQ monitors board meetings, agendas, budgets, and capital plans from 100,000+ state and local agencies and surfaces capital projects pre-RFPs in Missouri as soon as they appear — months before they reach bid portals.