Airport approves terminal project change order
- Disclosed value
- $81,465.00 (change order); total revised contract amount $8,072,919.29
- From minutes
- Document date
- Apr 14, 2026
The 30-second brief
The Westmoreland County Airport Authority approved Change Order No. 10A with Allegheny Construction Group for $81,465.00 to add drilling and monitoring well surveying required by DEP for an underground storage tank removal, bringing the terminal project contract total to $8,072,919.29. The work supports the ongoing terminal addition and improvements project at Arnold Palmer Regional Airport.
Allegheny Construction Group holds this construction contract with Westmoreland County Airport Authority.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $81,465.00 (change order); total revised contract amount $8,072,919.29
- Document date
- April 14, 2026
- Source document
- Westmoreland County Airport Authority Minutes Regularly Scheduled Meeting 2026-04-14 (Minutes)
Allegheny Construction Group's other public contracts
More Westmoreland County Airport Authority contracts
Questions about this contract
Who was awarded the construction contract by Westmoreland County Airport Authority?
Allegheny Construction Group was awarded this construction contract by Westmoreland County Airport Authority, as recorded on April 14, 2026. The contract value is $81,465.00 (change order); total revised contract amount $8,072,919.29.
How much is the Allegheny Construction Group contract with Westmoreland County Airport Authority worth?
The Allegheny Construction Group contract with Westmoreland County Airport Authority is valued at $81,465.00 (change order); total revised contract amount $8,072,919.29, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Westmoreland County Airport Authority Minutes Regularly Scheduled Meeting 2026-04-14 (Minutes), dated April 14, 2026 from Westmoreland County Airport Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Allegheny Construction Group hold?
Allegheny Construction Group may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Westmoreland County Airport Authority currently buying?
Explore Westmoreland County Airport Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.