Metro Builders Sativa Well Treatment Project Remains Ongoing
- Disclosed value
- $4,075,215; change orders totaling $610,074, including 40 change orders totaling $419,740.83
- From agendapacket
- Document date
- Oct 12, 2026
The 30-second brief
WRD reported that Metro Builders was awarded the Sativa Water System Well 5 treatment project for $4,075,215. The project has accumulated change orders and remains in startup activities after well clogging was identified.
Metro Builders holds this construction contract with Water Replenishment District of Southern California. Its other public contracts on record include work for Water Replenishment District Of Southern California and Palmdale Water District.
Term as filed: Notice to Proceed issued May 1, 2023; completion date extended to April 30, 2026, later updated to July 21, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $4,075,215; change orders totaling $610,074, including 40 change orders totaling $419,740.83
- Document date
- October 12, 2026
- Term
- Notice to Proceed issued May 1, 2023; completion date extended to April 30, 2026, later updated to July 21, 2026
- Vendor
- Metro Builders
- Source document
- Water Replenishment District of Southern California AgendaPacket Groundwater Quality Committee Meeting 2026-10-13 (AgendaPacket)
Metro Builders's other public contracts
More Water Replenishment District of Southern California contracts
Questions about this contract
Who was awarded the construction contract by Water Replenishment District of Southern California?
Metro Builders was awarded this construction contract by Water Replenishment District of Southern California, as recorded on October 12, 2026. The contract value is $4,075,215; change orders totaling $610,074, including 40 change orders totaling $419,740.83.
How much is the Metro Builders contract with Water Replenishment District of Southern California worth?
The Metro Builders contract with Water Replenishment District of Southern California is valued at $4,075,215; change orders totaling $610,074, including 40 change orders totaling $419,740.83, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Water Replenishment District of Southern California AgendaPacket Groundwater Quality Committee Meeting 2026-10-13 (AgendaPacket), dated October 12, 2026 from Water Replenishment District of Southern California. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Metro Builders hold?
Metro Builders may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Water Replenishment District of Southern California currently buying?
Explore Water Replenishment District of Southern California's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.