Disclosed value
T&M (time and material); original contract sum $1,184,000.00; change order amount to be determined; new contract sum TBD
From staffreport
Document date
Oct 19, 2026

The 30-second brief

What it covers

The Town of Wilton is seeking Board of Selectmen approval for Sav-Mor Cooling Heating, Inc. to replace leaking Cider Mill chiller piping on a time-and-material basis. Change Order #260032-2 will increase the $1,184,000 contract by an amount to be determined, with funding from the Cider Mill Chiller Replacement Capital Bonded fund.

Who holds it

Sav-mor Cooling Heating Inc holds this construction contract with Town of Wilton. Its other public contracts on record include work for Sharon School District.

What happens next

Term as filed: Contract dated June 23, 2026; change order adds 0 days.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
T&M (time and material); original contract sum $1,184,000.00; change order amount to be determined; new contract sum TBD
Document date
October 19, 2026
Term
Contract dated June 23, 2026; change order adds 0 days
Vendor
Sav-mor Cooling Heating Inc
Source document
Town of Wilton StaffReport Cider Mill Chiller Piping Replacement 2026-10-19 (StaffReport)

Sav-mor Cooling Heating Inc's other public contracts

More Town of Wilton contracts

Questions about this contract

Who was awarded the construction contract by Town of Wilton?

Sav-mor Cooling Heating Inc was awarded this construction contract by Town of Wilton, as recorded on October 19, 2026. The contract value is T&M (time and material); original contract sum $1,184,000.00; change order amount to be determined; new contract sum TBD.

How much is the Sav-mor Cooling Heating Inc contract with Town of Wilton worth?

The Sav-mor Cooling Heating Inc contract with Town of Wilton is valued at T&M (time and material); original contract sum $1,184,000.00; change order amount to be determined; new contract sum TBD, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in Town of Wilton StaffReport Cider Mill Chiller Piping Replacement 2026-10-19 (StaffReport), dated October 19, 2026 from Town of Wilton. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 1 more question

What is Town of Wilton currently buying?

Explore Town of Wilton's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →