Lincoln Approves Hutter Ledge Removal Change Order
Town of LincolnCity · Lincoln, MA- Disclosed value
- Not to exceed $100,000
- From minutes
- Document date
- Aug 12, 2026
The 30-second brief
The Town of Lincoln approved a change order to Hutter Construction’s contract for up to $100,000 to remove ledge encountered during septic tank and pump structure excavation. Blasting is tentatively scheduled for the week of August 24, 2026, with work expected to take no more than five business days.
Hutter Construction holds this construction contract with Town of Lincoln. Its other public contracts on record include work for Town of Westford and Strafford County.
Term as filed: Tentatively planned for the week of August 24, 2026; estimated duration no more than 5 business days.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Not to exceed $100,000
- Document date
- August 12, 2026
- Term
- Tentatively planned for the week of August 24, 2026; estimated duration no more than 5 business days
- Vendor
- Hutter Construction
- Agency
- Town of Lincoln
- Source document
- Town of Lincoln Minutes Community Center Building Committee August 12, 2026 (Minutes)
Hutter Construction's other public contracts
More Town of Lincoln contracts
Questions about this contract
Who was awarded the construction contract by Town of Lincoln?
Hutter Construction was awarded this construction contract by Town of Lincoln, as recorded on August 12, 2026. The contract value is Not to exceed $100,000.
How much is the Hutter Construction contract with Town of Lincoln worth?
The Hutter Construction contract with Town of Lincoln is valued at Not to exceed $100,000, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record, structured as a not-to-exceed (ceiling) agreement.
Where was this contract approved?
This contract appears in Town of Lincoln Minutes Community Center Building Committee August 12, 2026 (Minutes), dated August 12, 2026 from Town of Lincoln. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Hutter Construction hold?
Hutter Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Town of Lincoln currently buying?
Explore Town of Lincoln's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.