CONTRACTAMENDED

Lincoln Approves Hutter Ledge Removal Change Order

Town of Lincoln
Disclosed value
Not to exceed $100,000
From minutes
Document date
Aug 12, 2026

The 30-second brief

What it covers

The Town of Lincoln approved a change order to Hutter Construction’s contract for up to $100,000 to remove ledge encountered during septic tank and pump structure excavation. Blasting is tentatively scheduled for the week of August 24, 2026, with work expected to take no more than five business days.

Who holds it

Hutter Construction holds this construction contract with Town of Lincoln. Its other public contracts on record include work for Town of Westford and Strafford County.

What happens next

Term as filed: Tentatively planned for the week of August 24, 2026; estimated duration no more than 5 business days.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Not to exceed $100,000
Document date
August 12, 2026
Term
Tentatively planned for the week of August 24, 2026; estimated duration no more than 5 business days
Source document
Town of Lincoln Minutes Community Center Building Committee August 12, 2026 (Minutes)

Hutter Construction's other public contracts

More Town of Lincoln contracts

Questions about this contract

Who was awarded the construction contract by Town of Lincoln?

Hutter Construction was awarded this construction contract by Town of Lincoln, as recorded on August 12, 2026. The contract value is Not to exceed $100,000.

How much is the Hutter Construction contract with Town of Lincoln worth?

The Hutter Construction contract with Town of Lincoln is valued at Not to exceed $100,000, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record, structured as a not-to-exceed (ceiling) agreement.

Where was this contract approved?

This contract appears in Town of Lincoln Minutes Community Center Building Committee August 12, 2026 (Minutes), dated August 12, 2026 from Town of Lincoln. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Hutter Construction hold?

Hutter Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Town of Lincoln currently buying?

Explore Town of Lincoln's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →