CONTRACTAMENDED

Carbondale Aquatic Center Contract Amended with AD Miller

Town of Carbondale logoTown of Carbondale
Disclosed value
$13,419,571.12 total project budget; Change Order #008 net increase to GMP $49,077.61; PCO #033 $9,335; Construction Contingency balance $12,263.85 after changes
From report
Document date
May 1, 2026

The 30-second brief

What it covers

The Town of Carbondale’s aquatic center project with General Contractor AD Miller has been amended through Change Order #008, adding $49,077.61 to the Guaranteed Maximum Price while keeping the total project budget at $13,419,571.12. Additional contingency-funded scope, including PCO #033 and Kalwall and landscape-related work, is being incorporated as the project approaches substantial completion in May 2026.

Who holds it

Ad Miller holds this construction contract with Town of Carbondale. Its other public contracts on record include work for Denver County School District 1.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$13,419,571.12 total project budget; Change Order #008 net increase to GMP $49,077.61; PCO #033 $9,335; Construction Contingency balance $12,263.85 after changes
Document date
May 1, 2026
Vendor
Ad Miller
Source document
Carbondale Aquatic Center Project Update Report 2026-05-01 (Report)

Ad Miller's other public contracts

More Town of Carbondale contracts

Questions about this contract

Who was awarded the construction contract by Town of Carbondale?

Ad Miller was awarded this construction contract by Town of Carbondale, as recorded on May 1, 2026. The contract value is $13,419,571.12 total project budget; Change Order #008 net increase to GMP $49,077.61; PCO #033 $9,335; Construction Contingency balance $12,263.85 after changes.

How much is the Ad Miller contract with Town of Carbondale worth?

The Ad Miller contract with Town of Carbondale is valued at $13,419,571.12 total project budget; Change Order #008 net increase to GMP $49,077.61; PCO #033 $9,335; Construction Contingency balance $12,263.85 after changes, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Carbondale Aquatic Center Project Update Report 2026-05-01 (Report), dated May 1, 2026 from Town of Carbondale. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Ad Miller hold?

Ad Miller may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Town of Carbondale currently buying?

Explore Town of Carbondale's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.