CONTRACTAMENDED

Harper General Contractors Project Contract Amended

Town of Burnsville logoTown of Burnsville
Disclosed value
Original contract $1,995,089.00; approved change orders $183,452.57; revised contract amount $2,178,452.57
From agendapacket
Document date
Sep 3, 2026

The 30-second brief

What it covers

Burnsville's monthly project report shows Harper General Contractors' Police Station and Public Works construction contract increased to $2,178,452.57 after $183,452.57 in approved change orders. The project had a projected completion date of September 8, 2026, with sitework and punch-list activities remaining.

Who holds it

Harper General Contractors holds this construction contract with Town of Burnsville. Its other public contracts on record include work for Spartanburg School District 5 and Town of Canton.

What happens next

Term as filed: Original contract duration: 305 days; approved schedule changes: 184 days; projected completion September 8, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Original contract $1,995,089.00; approved change orders $183,452.57; revised contract amount $2,178,452.57
Document date
September 3, 2026
Term
Original contract duration: 305 days; approved schedule changes: 184 days; projected completion September 8, 2026
Source document
Burnsville Town Council AgendaPacket Regular Meeting September 3, 2026 (AgendaPacket)

Harper General Contractors's other public contracts

More Town of Burnsville contracts

Questions about this contract

Who was awarded the construction contract by Town of Burnsville?

Harper General Contractors was awarded this construction contract by Town of Burnsville, as recorded on September 3, 2026. The contract value is Original contract $1,995,089.00; approved change orders $183,452.57; revised contract amount $2,178,452.57.

How much is the Harper General Contractors contract with Town of Burnsville worth?

The Harper General Contractors contract with Town of Burnsville is valued at Original contract $1,995,089.00; approved change orders $183,452.57; revised contract amount $2,178,452.57, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Burnsville Town Council AgendaPacket Regular Meeting September 3, 2026 (AgendaPacket), dated September 3, 2026 from Town of Burnsville. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Harper General Contractors hold?

Harper General Contractors may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Town of Burnsville currently buying?

Explore Town of Burnsville's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →