CONTRACTAPPROVED

Town of Bourne Awards Construction Contract to Jj Cardosi (August 2026)

Town of Bourne
Disclosed value
GC contract is $11,590,300; original value was $14,181,000; reduced by $2,691,200; credit change order of $103,000
From minutes
Approved
Aug 11, 2026
Renews
Free account

The 30-second brief

What it covers

The Southside Fire Station Building Committee approved JJ Cardosi for the HVAC work and also approved a $103,000 credit change order. The revised general contractor contract amount is $11,590,300, with substantial completion set for September 6, 2027.

Who holds it

Jj Cardosi holds this construction contract with Town of Bourne. Its other public contracts on record include work for Nantucket Public Schools MA and Upper Cape Cod Regional Technical School.

What happens next

The renewal date is on record. A free account shows it, with the renewals for every Town of Bourne contract.

Renewal date on recordLocked

Know when this contract comes back up.

See the renewal date

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
GC contract is $11,590,300; original value was $14,181,000; reduced by $2,691,200; credit change order of $103,000
Document date
August 11, 2026
Term
Substantial completion date of September 6th, 2027; no change in contract time
Renews
Free account
Source document
Town of Bourne Southside Fire Station Building Committee Minutes Southside Fire Station Building Committee Meeting 2026-08-11 (Minutes)

Jj Cardosi's other public contracts

More Town of Bourne contracts

Questions about this contract

Who was awarded the construction contract by Town of Bourne?

Jj Cardosi was awarded this construction contract by Town of Bourne, as recorded on August 11, 2026. The contract value is GC contract is $11,590,300; original value was $14,181,000; reduced by $2,691,200; credit change order of $103,000.

How much is the Jj Cardosi contract with Town of Bourne worth?

The Jj Cardosi contract with Town of Bourne is valued at GC contract is $11,590,300; original value was $14,181,000; reduced by $2,691,200; credit change order of $103,000, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Town of Bourne Southside Fire Station Building Committee Minutes Southside Fire Station Building Committee Meeting 2026-08-11 (Minutes), dated August 11, 2026 from Town of Bourne. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Jj Cardosi hold?

Jj Cardosi may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Town of Bourne currently buying?

Explore Town of Bourne's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.