Town of Bourne Awards Construction Contract to Jj Cardosi (August 2026)
Town of BourneCity · Buzzards Bay, MA- Disclosed value
- GC contract is $11,590,300; original value was $14,181,000; reduced by $2,691,200; credit change order of $103,000
- From minutes
- Approved
- Aug 11, 2026
- Renews
- Free account
The 30-second brief
The Southside Fire Station Building Committee approved JJ Cardosi for the HVAC work and also approved a $103,000 credit change order. The revised general contractor contract amount is $11,590,300, with substantial completion set for September 6, 2027.
Jj Cardosi holds this construction contract with Town of Bourne. Its other public contracts on record include work for Nantucket Public Schools MA and Upper Cape Cod Regional Technical School.
The renewal date is on record. A free account shows it, with the renewals for every Town of Bourne contract.
Know when this contract comes back up.
See the renewal dateFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- GC contract is $11,590,300; original value was $14,181,000; reduced by $2,691,200; credit change order of $103,000
- Document date
- August 11, 2026
- Term
- Substantial completion date of September 6th, 2027; no change in contract time
- Renews
- Free account
- Vendor
- Jj Cardosi
- Agency
- Town of Bourne
- Source document
- Town of Bourne Southside Fire Station Building Committee Minutes Southside Fire Station Building Committee Meeting 2026-08-11 (Minutes)
Jj Cardosi's other public contracts
More Town of Bourne contracts
Questions about this contract
Who was awarded the construction contract by Town of Bourne?
Jj Cardosi was awarded this construction contract by Town of Bourne, as recorded on August 11, 2026. The contract value is GC contract is $11,590,300; original value was $14,181,000; reduced by $2,691,200; credit change order of $103,000.
How much is the Jj Cardosi contract with Town of Bourne worth?
The Jj Cardosi contract with Town of Bourne is valued at GC contract is $11,590,300; original value was $14,181,000; reduced by $2,691,200; credit change order of $103,000, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Town of Bourne Southside Fire Station Building Committee Minutes Southside Fire Station Building Committee Meeting 2026-08-11 (Minutes), dated August 11, 2026 from Town of Bourne. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Jj Cardosi hold?
Jj Cardosi may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Town of Bourne currently buying?
Explore Town of Bourne's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.