Gilleland Smith Submits Water Plant Rehabilitation Bid
Spring Creek Forest PudUtility District · Austin, TX- Disclosed value
- $1,114,500.00
- From agendapacket
- Document date
- Oct 13, 2026
- Term
- 200 days to substantial completion
The 30-second brief
Gilleland Smith Construction Inc submitted a $1,114,500 bid for the District's Water Plant No. 2 rehabilitation project. The engineer's recommendation identified Schier Construction Company, Inc. as the low bidder.
Gilleland Smith Construction Inc holds this construction contract with Spring Creek Forest Pud. Its other public contracts on record include work for Northwest Freeway Mud and Harris County Mud 345.
Term as filed: 200 days to substantial completion.
See who signed off on this $1.1M contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $1,114,500.00
- Document date
- October 13, 2026
- Term
- 200 days to substantial completion
- Agency
- Spring Creek Forest Pud
- Source document
- Spring Creek Forest Public Utility District AgendaPacket Board Meeting 2026-10-13 (AgendaPacket)
Gilleland Smith Construction Inc's other public contracts
More Spring Creek Forest Pud contracts
Questions about this contract
Who was awarded the construction contract by Spring Creek Forest Pud?
Gilleland Smith Construction Inc was awarded this construction contract by Spring Creek Forest Pud, as recorded on October 13, 2026. The contract value is $1,114,500.00.
How much is the Gilleland Smith Construction Inc contract with Spring Creek Forest Pud worth?
The Gilleland Smith Construction Inc contract with Spring Creek Forest Pud is valued at $1,114,500.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Spring Creek Forest Public Utility District AgendaPacket Board Meeting 2026-10-13 (AgendaPacket), dated October 13, 2026 from Spring Creek Forest Pud. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Gilleland Smith Construction Inc hold?
Gilleland Smith Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Spring Creek Forest Pud currently buying?
Explore Spring Creek Forest Pud's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.