Pipeline Construction Change Orders Amend RE Chaffee Contract
- Disclosed value
- ($64,282) net change from construction change orders #1 and #2; original contract $1,278,295
- From staffreport
- Document date
- Nov 7, 2026
- Term
- August 3, 2025 – October 9, 2026
The 30-second brief
South Coast Water District processed construction change orders #1 and #2 with RE Chaffee Construction, Inc. The changes produced a net credit of $64,282 against the original $1,278,295 contract, for an estimated revised value of $1,214,013.
Re Chaffee Construction Inc holds this construction contract with South Coast Water District. Its other public contracts on record include work for Phelan Piñon Hills Community Services District.
Term as filed: August 3, 2025 – October 9, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- ($64,282) net change from construction change orders #1 and #2; original contract $1,278,295
- Document date
- November 7, 2026
- Term
- August 3, 2025 – October 9, 2026
- Source document
- South Coast Water District Staff Report Joint Regional Water Supply System Local Transmission Main Pipeline Replacement At Calle Vista Torito Project Notice Of Completion 2026-11-12 (StaffReport)
Re Chaffee Construction Inc's other public contracts
More South Coast Water District contracts
Questions about this contract
Who was awarded the construction contract by South Coast Water District?
Re Chaffee Construction Inc was awarded this construction contract by South Coast Water District, as recorded on November 7, 2026. The contract value is ($64,282) net change from construction change orders #1 and #2; original contract $1,278,295.
How much is the Re Chaffee Construction Inc contract with South Coast Water District worth?
The Re Chaffee Construction Inc contract with South Coast Water District is valued at ($64,282) net change from construction change orders #1 and #2; original contract $1,278,295, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in South Coast Water District Staff Report Joint Regional Water Supply System Local Transmission Main Pipeline Replacement At Calle Vista Torito Project Notice Of Completion 2026-11-12 (StaffReport), dated November 7, 2026 from South Coast Water District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Re Chaffee Construction Inc hold?
Re Chaffee Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is South Coast Water District currently buying?
Explore South Coast Water District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.